5.2.
Public Works Committee
Meeting Date: 09/19/2023
   
Primary Strategic Plan Initiative: {ud_pd8}

Title:

Receive Updates on Improvement Projects, Studies and Items of Interest

Purpose/Background:

The purpose of this case is to update the Public Works Committee on current and proposed City, County and MnDOT improvement projects and studies, and on other items of interest to the Committee.

City Improvement Projects
  • 2024 PMP Projects
    • Design in progress on 9 projects
  • 161st Avenue Reconstruction (IP #23-01)
    • Construction substantially complete
    • PACT Charter opened Monday, September 11th
  • Central Park Parking Lot Reconstruction (IP #23-02)
    • Preconstruction meeting conducted last week
    • Fall 2023 construction proposed
  • 167th Avenue Reconstruction (IP #23-04)
    • Construction in progress
    • Completion anticipated mid-October
  • Barthels Rum River Acres 2nd Reconstruction (IP #23-05)
    • Construction in progress
    • Completion anticipated late September
  • 2023 MSA Pavement Overlay Improvements (IP #23-06)
    • Construction in progress
  • Whispering Pines Estates Plat 3 Reconstructions (IP #23-10)
    • Construction in progress
  • Trott Brook Crossing Sanitary Sewer Lift Station Improvements (IP #23-11)
    • Construction in progress
    • Fall 2023 final completion
  • HY-10 Ramsey Improvements (IP #23-12)
    • Construction in progress
    • Summer/Fall 2023 construction
  • Highway 47 Sound Wall north of Xkimo Street (IP #22-17)
    • MnDOT Cooperative Construction Agreement required
    • Staff anticipates requesting Council approval to authorize bids Spring/Summer 2024
  • WTP Trunk Watermain Improvements (#21-08)
    • Council request to approve plans and authorize re-bidding anticipated Fall 2023
  • Centralized Water Treatment Plant (#21-09)
    • Construction in progress
    • Substantial completion scheduled for May 1, 2025
    • Final completion scheduled for August 1, 2025
  • Ramsey Gateway Highway 10 Improvements (IP #20-11)
    • Construction started Summer 2023 and will end early 2026 (2024 - 2025 majority)
    • Riverdale Drive east of SLB & temp US 10 widening Summer/Fall 2023
    • Public Open Houses are being scheduled for Winter 2024
 
City of Anoka Improvement Projects
  • Highway 47 Corridor Improvements
    • 3-lane design proposed south of Bunker Lake Boulevard
    • City received regional solicitation funds for 2027 construction
    • Signal system at McKinley Street is proposed to be permanent
    • Anoka webpage https://clients.bolton-menk.com/anokahwy47/
 
Anoka County Improvement Projects
  • Roundabout at Armstrong Boulevard/CSAH 83 and Alpine Drive (IP #23-03)
    • Construction substantially complete
    • Construction complete Fall 2023
 
MnDOT Improvement Projects  
Studies & Items of Interest
  • Pothole Patching Updates
    • Staff will summarize pothole patching work completed to date and plans to prepare for next spring 
  • Sunfish Lake Sedimentation Basin Improvements
    • Property owner indicated interest in filling swale and grading sedimentation basin
    • Staff delineated rear property line last Fall and notified property owner
    • Staff continues to try contacting property owner
  • Elk River Highway 10 Corridor Study

Notification:

N/A

Time Frame/Observations/Alternatives:

Staff estimates up to 10 minutes will be needed for updates and discussion.  

Funding Source:

N/A

Recommendation:

N/A

Outcome/Action:

No formal action required.  For Committee review and discussion purposes only.  

Attachments

No file(s) attached.

Form Review

Inbox Reviewed By Date
Brian Hagen Brian Hagen 09/14/2023 03:22 PM
Form Started By:
Bruce Westby
Started On:
09/14/2023 02:21 PM
Final Approval Date:
09/14/2023