5.22.
| CC Regular Session |
| Meeting Date: | 09/26/2023 |
| Primary Strategic Plan Initiative: | {ud_pd4} |
Information
Title:
Adopt Resolution #23-232 Authorizing Partial Payment to Magney Construction, Inc. for Improvement Project #21-09, Centralized Water Treatment Plant
Purpose/Background:
Resolution and Pay Request attached.
Recommendation:
The Resident Project Representative from Advanced Engineering and Environmental Services (AE2S) has inspected the completed work and recommends partial payment #3 to Magney Construction, Inc. for said project in the amount of $858,896.90.
Outcome/Action:
Motion to adopt Resolution #23-232 authorizing partial payment #3 to Magney Construction, Inc. for Improvement Project #21-09, Centralized Water Treatment Plant in the amount of $858,896.90.
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Bruce Westby | Bruce Westby | 09/21/2023 10:37 AM |
| Brian Hagen | Brian Hagen | 09/21/2023 11:12 AM |
- Form Started By:
- Stacie Damjanovich
- Started On:
- 09/19/2023 09:03 AM
- Final Approval Date:
- 09/21/2023