Skip to main content

AgendaQuick™

View Agenda Item

5.5.
CC Regular Session
Meeting Date: 11/28/2023
   
Primary Strategic Plan Initiative: {ud_pd7}

Information

Title

Adopt Resolution #23-224, Approving Final Payment to A & B Construction LTD, for IP #22-10, Public Works Salt Shed. 

Purpose/Background:

Resolution and Pay Request Attached.

Observations/Alternatives:

Issuing final payment will be contingent on receipt of the following items from contractor, A & B Construction LTD.


1. IC-134 (Contractor's Withholding Affidavit showing compliance with the provisions of Minnesota Statue 290.92 requiring withholding state income tax).
2. Waiver of Mechanic's Lien Rights (Affidavits that all claims against contractor, A & B Construction LTD, by reasons of the contract have been fully paid or satisfactorily secured).

Following receipt of these items, final payment will be issued. 

Recommendation:

The Senior Engineering Technician has inspected the completed work and recommends final payment to A & B Construction LTD of Harper Iowa, for Improvement Project #22-10, Public Works Salt Shed, in the amount of $24,826.50.

Action:

Motion to adopt Resolution #23-224 approving final payment to A & B Construction LTD for IP #22-10, Public Works Salt Shed in the amount of $24,826.50.

Attachments

Form Review

Inbox Reviewed By Date
Bruce Westby Bruce Westby 11/22/2023 01:35 PM
Brian Hagen Brian Hagen 11/22/2023 02:07 PM
Form Started By:
Stacie Damjanovich
Started On:
09/28/2023 09:44 AM
Final Approval Date:
11/22/2023