Receive Updates on Improvement Projects, Studies and Items of Interest
Purpose/Background:
The purpose of this case is to update the Public Works Committee on current and proposed City, County and MnDOT improvement projects and studies, and on other items of interest to the Committee.
City Improvement Projects
City Improvement Projects
- 2024 PMP Projects
- Design in progress on 9 projects è noticing open houses
- 161st Avenue Reconstruction (IP #23-01)
- Construction substantially complete
- Punch list work in progress
- Central Park Parking Lot Reconstruction (IP #23-02)
- Construction substantially complete
- Punch list work in progress
- 167th Avenue Reconstruction (IP #23-04)
- Construction in progress
- Completion anticipated mid t late-October
- Barthels Rum River Acres 2nd Reconstruction (IP #23-05)
- Construction substantially complete
- Punch list work in progress
- 2023 MSA Pavement Overlay Improvements (IP #23-06)
- Construction substantially complete
- Punch list work in progress
- Whispering Pines Estates Plat 3 Reconstructions (IP #23-10)
- Construction substantially complete
- Punch list work in progress
- Trott Brook Crossing Sanitary Sewer Lift Station Improvements (IP #23-11)
- Construction in progress
- Fall 2023 final completion
- HY-10 Ramsey Improvements (IP #23-12)
- Construction substantially complete
- Punch list work in progress
- COR Mass Grading (IP #23-20)
- Approximately 50% complete
- Encountered silty sands in middle of pond è revise pond bottom grades?
- Completion anticipated by end of 2023
- Highway 47 Sound Wall north of Xkimo Street (IP #22-17)
- MnDOT Cooperative Construction Agreement required
- Staff anticipates requesting Council approval to authorize bids Spring/Summer 2024
- WTP Trunk Watermain Improvements (#21-08)
- Advertised for bids
- Bid opening November 1, 2023
- Council to consider awarding Contract November 14, 2023
- Centralized Water Treatment Plant (#21-09)
- Construction in progress
- Substantial completion scheduled for May 1, 2025
- Final completion scheduled for August 1, 2025
- Ramsey Gateway Highway 10 Improvements (IP #20-11)
- Riverdale Drive east of SLB & temp US 10 widening Summer/Fall 2023
- Ames Construction under contract October 11, 2023
- Preconstruction meeting held October 12, 2023
- Construction starting October 16, 2023
- Construction completion anticipated June 2026
-
City of Anoka Improvement Projects - Highway 47 Corridor Improvements
- 3-lane design proposed south of Bunker Lake Boulevard
- City received regional solicitation funds for 2027 construction
- Signal system at McKinley Street is proposed to be permanent
- Anoka webpage https://clients.bolton-menk.com/anokahwy47/
-
Anoka County Improvement Projects - Roundabout at Armstrong Boulevard/CSAH 83 and Alpine Drive (IP #23-03)
- Construction substantially complete
- Punch list work in progress
-
MnDOT Improvement Projects - Anoka Solution Highway 10 Improvements
- Substantial completion November 2023
- Final completion Spring 2024
- Anoka webpage https://clients.bolton-menk.com/hwy10/
- MnDOT webpage http://www.dot.state.mn.us/metro/projects/hwy10-anoka/
- US 10 / 169 & Ferry Street / TH 47 Interchange
- Final completion Spring 2024
- MnDOT webpage http://www.dot.state.mn.us/metro/projects/hwy10-anoka/
- Ferry Street / Trunk Highway 47 Grade Separation @ BNSF Rail Crossing
- Preliminary design suspended; exploring S-curve realignment and stormwater impacts
- $45M in bonds authorized October 2020
- Construction proposed for 2024 or later
- MnDOT webpage http://www.dot.state.mn.us/metro/projects/hwy47rr-anoka/
- Rum River Bridge Replacement
- Three lanes each direction
- Final completion Spring 2024
- MnDOT webpage http://www.dot.state.mn.us/metro/projects/hwy10-anoka/
-
Studies & Items of Interest - Sunfish Lake Sedimentation Basin Improvements
- Property owner indicated interest in filling swale and grading sedimentation basin
- Staff delineated rear property line last Fall and notified property owner
- Staff continues to try contacting property owner
- Elk River Highway 10 Corridor Study
- Staff will present final report when available (November 2023?)
- Study website https://www.highway10corridorstudy.com/
Time Frame/Observations/Alternatives:
Staff estimates up to 10 minutes will be needed for updates and discussion.
Recommendation:
NA
Outcome/Action:
No formal action required. For Committee review and discussion purposes only.
Attachments
No file(s) attached.
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Brian Hagen | Brian Hagen | 10/12/2023 03:11 PM |
- Form Started By:
- Bruce Westby
- Started On:
- 10/10/2023 04:07 PM
- Final Approval Date:
- 10/12/2023