Title
Adopt Resolution #23-262 Approving Partial Payment to Diversified Paving, Inc. for Pavement Maintenance Project #23-21; 2023 Deep Pothole Patching Contracted Services.
Purpose/Background:
Resolution and Pay Request attached.
Recommendation:
The Streets Supervisor has inspected the completed work and recommends partial payment No. 1 to Diversified Paving, Inc. for pavement maintenance project #23-21, 2023 Deep Pothole Patching Contracted Services, in the amount of $424,888.92.
Action:
Motion to adopt Resolution #23-262 approving partial payment No. 1 to Diversified Paving, Inc. for pavement maintenance project #23-21; 2023 Deep Pothole Patching Contracted Services, in the amount of $424,888.92.
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Bruce Westby | Bruce Westby | 10/19/2023 06:36 AM |
| Brian Hagen | Brian Hagen | 10/19/2023 07:25 AM |
- Form Started By:
- Stacie Damjanovich
- Started On:
- 10/13/2023 10:03 AM
- Final Approval Date:
- 10/19/2023