5.17.
| CC Regular Session |
| Meeting Date: | 11/28/2023 |
| Primary Strategic Plan Initiative: | {ud_pd7} |
Information
Title
Adopt Resolution #23-295 Authorizing Partial Payment No. 5 To Magney Construction, Inc. for Improvement Project #21-09; Centralized Water Treatment Plant.
Purpose/Background:
Resolution and Pay Estimate #4 Attached.
Recommendation:
The Resident Project Representative from Advanced Engineering and Environmental Services (AE2S) has inspected the completed work and recommends partial payment #5 to Magney Construction, Inc. for said project in the amount of $647,228.35.
Action:
Motion to adopt Resolution #23-295 authorizing partial payment #5 to Magney Construction, Inc. of Chanhassen, Minnesota Improvement Project #21-09 Centralized Water Treatment Plant, in the amount of $647,228.35.
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Bruce Westby | Bruce Westby | 11/22/2023 01:39 PM |
| Brian Hagen | Brian Hagen | 11/22/2023 02:07 PM |
- Form Started By:
- Marsha Weidner
- Started On:
- 11/17/2023 10:16 AM
- Final Approval Date:
- 11/22/2023