5.18.
| CC Regular Session |
| Meeting Date: | 11/28/2023 |
| Primary Strategic Plan Initiative: | {ud_pd7} |
Information
Title
Adopt Resolution #23-297 Approving Plans and Specifications and Authorizing Advertisement for Bids for Barthel’s Rum River Acres and White Pines Estates Street Reconstructions, Improvement Project #24-01
Purpose/Background:
Purpose:
The purpose of this case is to adopt Resolution #23-297 approving plans and specifications and authorizing advertisement for bids for Barthel’s Rum River Acres and White Pines Estates Street Reconstructions, Improvement Project #24-01.
Background:
City Improvement Project #24-01 proposes to reconstruct the streets within the Barthel’s Rum River Acres and White Pines Estates subdivisions, generally located between 164th Lane and 165th Lane, adjacent to the Rum River. The 2023 – 2032 Capital Improvement Program (CIP) identifies the streets within these subdivisions for street reconstruction in 2024. Street segment summaries are attached to this case.
Project History
Pavement History
The streets within the Barthel’s Rum River Acres subdivision were built in 1982. The streets received an overlay improvement in 1997, the only other pavement maintenance was a crack seal / seal coat improvement in 2009. Maintenance crews have performed patching over the last several years, including extensive patching in 2023.
The streets within the White Pines Estates subdivision were built in 1977. Pavement maintenance has included initial crack seal / seal coat improvements in 1984 and 1992. An overlay was performed in 2001, the only pavement maintenance project since was a crack seal / seal coat improvement in 2009. Maintenance crews have performed patching as needed over the last several years.
Existing Conditions
The streets vary between 24 feet wide rural section and 31 feet wide urban section including bituminous curbing, totaling 1.33 miles in length. Traffic counts have not been taken, but Staff anticipates typical neighborhood traffic due to the location of the subdivision and lack of destinations which would increase traffic above normal.
Municipal sewer and water do not exist in the project area, and utility extensions to the area are not proposed. The existing drainage is through a combination of swales adjacent to the roadway, and on street drainage to curb cuts in the bituminous curbing area, as well as street crossing culverts. Additionally, Staff is aware of Northern Natural gas mainlines crossing in one location at 164th Lane, approximately 600 feet east of Trunk Highway 47.
Proposed Improvements
Staff review of the geotechnical report found generally sandy subsoil make up the roadway embankment throughout the project area. There are areas of silt and highly plastic clay below the roadway embankment zone. These would only impact the project if excavation goes deeper than 3 to 4 feet, generally for storm sewer installation. Where these soils are found during pipe installation, the plans call for subsoil corrections in the immediate areas, and have quantities built into the plans to accommodate such a circumstance.
In general, the current swales along the street within the Barthel’s Rum River Acres subdivision are not proposed to be re-graded as part of this project. Due to the nature of street reconstructions, the in-slopes will be disturbed approximately 3 to 5 feet off of the edge of pavement. No changes to the current drainage patterns are proposed. The existing culverts crossing the streets are proposed to be removed and replaced, this is to ensure the culverts will last at least through the proposed 60-year design life of the street.
The bituminous curbing within the White Pines Estates subdivision is proposed to be replaced with surmountable concrete curb and gutter. At driveways, a curb cut similar to what is typically placed in B-style curb will be placed to avoid a high transition from the roadway to driveways. Additionally, concrete storm sewer inlets and piping will be added to better drain the urban section streets. As discussed previously, Staff is anticipating some subsoil corrections will be necessary as part of the storm sewer construction. This will consist of removing the poor soils and replacing with select granular sand, which is proper pipe bedding material.
Restoration of the impacted boulevard areas will include a minimum of 4-inches topsoil and hydroseed with a residential turf seed mix. Though the pavement is generally going back to the same location and elevation, driveway aprons will be replaced to match into the new bituminous pavement as minor changes will occur. In general, driveway aprons will be going back 8 feet to tie the driveways into the new pavement.
The majority of stormwater within these subdivisions drain to a ditch located on 16512 Germanium Street. Existing there is a significant bump in the road at the culvert crossing location to this outlet, because of the lack of clearance above the pipe. This project proposes raising Germanium Street approximately 1-foot at this location to allow clearance over the new crossing pipe. This will require the driveway at 16512 to be replaced further back, and additional grading to match into the new roadway, however, work is still anticipated to be contained within the right-of-way.
Preliminary Schedule Remaining
Bid Opening
Staff proposes to open bids on February 21, 2024, and to present the bid results to City Council on February 27, 2024 for award of a construction contract to the lowest responsible bidder.
Final plans are not attached to this case to prevent potential bidders from downloading plans attached to the case to prepare and submit their bids, rather than purchasing the plans through QuestCDN, the electronic bidding software used by the City of Ramsey. This ensures all bidders are bidding off the same set of plans and all bidders are notified of any plan revisions (addenda) issued during the bidding process. Attached is the title sheet showing the scope of the improvements, as well as a plan sheet showing the typical sections, which includes information on the proposed pavement section. Plans are available upon request from the City Engineer.
The proposed improvements are designated as City Improvement Project #24-01, Barthel’s Rum River Acres and White Pines Estates Street Reconstructions.
The purpose of this case is to adopt Resolution #23-297 approving plans and specifications and authorizing advertisement for bids for Barthel’s Rum River Acres and White Pines Estates Street Reconstructions, Improvement Project #24-01.
Background:
City Improvement Project #24-01 proposes to reconstruct the streets within the Barthel’s Rum River Acres and White Pines Estates subdivisions, generally located between 164th Lane and 165th Lane, adjacent to the Rum River. The 2023 – 2032 Capital Improvement Program (CIP) identifies the streets within these subdivisions for street reconstruction in 2024. Street segment summaries are attached to this case.
Project History
- 2023 – 2032 Capital Improvement Program – listed as street reconstruction in 2024.
- June 13, 2023 Resolution #23-130, the Ramsey City Council accepted proposals for topographic survey of the project area.
- June 27, 2023 Resolution #23-129, the Ramsey City Council accepted proposals for geotechnical report of the project area.
- August 22, 2023 Resolution #23-197, the Ramsey City Council ordered Staff to prepare plans and specifications.
- October 10, 2023 Resolution #23-250, the Ramsey City Council accepted proposal for sewer cleaning and televising.
- November 21, 2023, the Ramsey Public Work Committee considered recommending City Council approval of plans and specifications and authorizing advertisement for bids.
Pavement History
The streets within the Barthel’s Rum River Acres subdivision were built in 1982. The streets received an overlay improvement in 1997, the only other pavement maintenance was a crack seal / seal coat improvement in 2009. Maintenance crews have performed patching over the last several years, including extensive patching in 2023.
The streets within the White Pines Estates subdivision were built in 1977. Pavement maintenance has included initial crack seal / seal coat improvements in 1984 and 1992. An overlay was performed in 2001, the only pavement maintenance project since was a crack seal / seal coat improvement in 2009. Maintenance crews have performed patching as needed over the last several years.
Existing Conditions
The streets vary between 24 feet wide rural section and 31 feet wide urban section including bituminous curbing, totaling 1.33 miles in length. Traffic counts have not been taken, but Staff anticipates typical neighborhood traffic due to the location of the subdivision and lack of destinations which would increase traffic above normal.
Municipal sewer and water do not exist in the project area, and utility extensions to the area are not proposed. The existing drainage is through a combination of swales adjacent to the roadway, and on street drainage to curb cuts in the bituminous curbing area, as well as street crossing culverts. Additionally, Staff is aware of Northern Natural gas mainlines crossing in one location at 164th Lane, approximately 600 feet east of Trunk Highway 47.
Proposed Improvements
Staff review of the geotechnical report found generally sandy subsoil make up the roadway embankment throughout the project area. There are areas of silt and highly plastic clay below the roadway embankment zone. These would only impact the project if excavation goes deeper than 3 to 4 feet, generally for storm sewer installation. Where these soils are found during pipe installation, the plans call for subsoil corrections in the immediate areas, and have quantities built into the plans to accommodate such a circumstance.
In general, the current swales along the street within the Barthel’s Rum River Acres subdivision are not proposed to be re-graded as part of this project. Due to the nature of street reconstructions, the in-slopes will be disturbed approximately 3 to 5 feet off of the edge of pavement. No changes to the current drainage patterns are proposed. The existing culverts crossing the streets are proposed to be removed and replaced, this is to ensure the culverts will last at least through the proposed 60-year design life of the street.
The bituminous curbing within the White Pines Estates subdivision is proposed to be replaced with surmountable concrete curb and gutter. At driveways, a curb cut similar to what is typically placed in B-style curb will be placed to avoid a high transition from the roadway to driveways. Additionally, concrete storm sewer inlets and piping will be added to better drain the urban section streets. As discussed previously, Staff is anticipating some subsoil corrections will be necessary as part of the storm sewer construction. This will consist of removing the poor soils and replacing with select granular sand, which is proper pipe bedding material.
Restoration of the impacted boulevard areas will include a minimum of 4-inches topsoil and hydroseed with a residential turf seed mix. Though the pavement is generally going back to the same location and elevation, driveway aprons will be replaced to match into the new bituminous pavement as minor changes will occur. In general, driveway aprons will be going back 8 feet to tie the driveways into the new pavement.
The majority of stormwater within these subdivisions drain to a ditch located on 16512 Germanium Street. Existing there is a significant bump in the road at the culvert crossing location to this outlet, because of the lack of clearance above the pipe. This project proposes raising Germanium Street approximately 1-foot at this location to allow clearance over the new crossing pipe. This will require the driveway at 16512 to be replaced further back, and additional grading to match into the new roadway, however, work is still anticipated to be contained within the right-of-way.
Preliminary Schedule Remaining
- Council Approves Plans and Specifications / Authorizes Ad for Bids
- November 28, 2023
- Staff Receives Bids
- February 21, 2024
- Council Awards Contract to the Lowest Responsible Bidder
- February 27, 2024
- Contractor Begins Construction
- Spring 2024
- Contractor Substantially Completes Construction
- New bituminous pavement in-place, topsoil and seed in-place
- August 2, 2024
- Contractor Final Completion
- Verify final restoration; punch list created
- August 30, 2024
Bid Opening
Staff proposes to open bids on February 21, 2024, and to present the bid results to City Council on February 27, 2024 for award of a construction contract to the lowest responsible bidder.
Final plans are not attached to this case to prevent potential bidders from downloading plans attached to the case to prepare and submit their bids, rather than purchasing the plans through QuestCDN, the electronic bidding software used by the City of Ramsey. This ensures all bidders are bidding off the same set of plans and all bidders are notified of any plan revisions (addenda) issued during the bidding process. Attached is the title sheet showing the scope of the improvements, as well as a plan sheet showing the typical sections, which includes information on the proposed pavement section. Plans are available upon request from the City Engineer.
The proposed improvements are designated as City Improvement Project #24-01, Barthel’s Rum River Acres and White Pines Estates Street Reconstructions.
Notification:
If Council approves plans and specifications and authorizes advertising for bids, bids will be advertised on Friday, December 1, and again on Friday December 8, 2023 in the City’s official newspaper, the Anoka Union Herald.
Additionally, letters will be mailed to property owners with updates on the project status. Engineering Staff maintains City improvement webpages with the most current project information, this can be found on the City website, Engineering Department page.
Additionally, letters will be mailed to property owners with updates on the project status. Engineering Staff maintains City improvement webpages with the most current project information, this can be found on the City website, Engineering Department page.
Observations/Alternatives:
Alternatives:
Motion to adopt Resolution #23-297 approving plans and specifications and authorizing advertisement for bids for Barthel’s Rum River Acres and White Pines Estates Street Reconstructions, Improvement Project #24-01.
Motion to adopt Resolution #23-297 approving plans and specifications and authorizing advertisement for bids for Barthel’s Rum River Acres and White Pines Estates Street Reconstructions, Improvement Project #24-01.
Funding Source:
Funding for this improvement is proposed to come from Pavement Management Funds and Stormwater Utility Funds.
Staff has completed an estimate based on final plans and anticipated 2024 construction costs, with a total estimated project cost of $1,505,111, which includes 23-percent indirect costs for administrative, engineering, finance, and legal costs. The CIP level estimated project costs were $1,160,063. This difference in CIP level and final plan level estimate was primarily due to more concrete curb and gutter and storm sewer required than anticipated. Final project costs will be dependent upon actual bid pricing and quantities.
Staff has completed an estimate based on final plans and anticipated 2024 construction costs, with a total estimated project cost of $1,505,111, which includes 23-percent indirect costs for administrative, engineering, finance, and legal costs. The CIP level estimated project costs were $1,160,063. This difference in CIP level and final plan level estimate was primarily due to more concrete curb and gutter and storm sewer required than anticipated. Final project costs will be dependent upon actual bid pricing and quantities.
- Street Project Costs $1,260,224
- Storm Sewer Project Costs $244,887
- Total Estimated Costs $1,505,111
Recommendation:
Staff recommends adopting Resolution #23-297 approving plans and specifications and authorizing advertisement for bids for Barthel’s Rum River Acres and White Pines Estates Street Reconstructions, Improvement Project #24-01.
On November 21, 2023 the Ramsey Public Works Committee reviewed the improvement project and recommended city council approve plans and specifications and authorize advertisement for bids for Barthel’s Rum River Acres and White Pines Estates Street Reconstructions, Improvement Project #24-01
On November 21, 2023 the Ramsey Public Works Committee reviewed the improvement project and recommended city council approve plans and specifications and authorize advertisement for bids for Barthel’s Rum River Acres and White Pines Estates Street Reconstructions, Improvement Project #24-01
Action:
Adopt Resolution #23-297 approving plans and specifications and authorizing advertisement for bids for Barthel’s Rum River Acres and White Pines Estates Street Reconstructions, Improvement Project #24-01.
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Bruce Westby | Bruce Westby | 11/22/2023 01:40 PM |
| Brian Hagen | Brian Hagen | 11/22/2023 02:07 PM |
- Form Started By:
- Joe Feriancek
- Started On:
- 11/17/2023 12:32 PM
- Final Approval Date:
- 11/22/2023