5.10.
| CC Regular Session |
| Meeting Date: | 01/23/2024 |
| Primary Strategic Plan Initiative: | {ud_pd7} |
Information
Title
Adopt Resolution #24-002 Approving Partial Payment to Meyer Contracting, Inc. for Improvement Project #23-11; Lift Station #10 Improvements.
Purpose/Background:
Resolution and Pay Request Attached.
Recommendation:
The Senior Engineering Technician has inspected the completed work and recommends partial payment to Meyer Contracting, Inc. for improvement project #23-11, Lift Station #10 Improvements in the amount of $59,874.74.
Action:
Motion to adopt Resolution #24-002 approving partial payment to Meyer Contracting, Inc. for improvement project #23-11, Lift Station #10 Improvements in the amount of $59,874.74.
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Bruce Westby | Bruce Westby | 01/18/2024 01:33 PM |
| Brian Hagen | Kathy Schmitz | 01/18/2024 01:46 PM |
- Form Started By:
- Stacie Damjanovich
- Started On:
- 12/01/2023 11:21 AM
- Final Approval Date:
- 01/18/2024