Receive Updates on Improvement Projects, Studies and Items of Interest

Purpose/Background:

The purpose of this case is to update the Public Works Committee on current and proposed City, County and MnDOT improvement projects and studies, and on other items of interest to the Committee.

City Improvement Projects
  • 2024 PMP Projects
    • 11 projects total (7 recons, 2 overlays, 1 crack seal, 1 rejuvenator)
    • Public open houses conducted for street reconstruction projects
  • #24-01 Barthel’s Rum River Acres & White Pine Estates
    • Bid opening February 21, 2024
    • Award contract February 27, 2024
  • #24-02 Halls Dover Acres Street Reconstruction
    • Bid opening February 21, 2024
    • Award contract February 27, 2024
  • #24-03 2024 NE Ramsey Street Reconstruction
    • Plan preparation in progress (Hakanson Anderson)
  • #24-04 180th Lane Drainage Improvements
    • Design in progress
  • #24-05 Xkimo St MSA (TH47 to 142nd Avenue) Reconstruction
    • Plan preparation in progress (Hakanson Anderson)
  • #24-06 2024 MSA Pavement Overlay Improvements (McKinley St)
    • Plan preparation in progress
  • #24-07 2024 Neighborhood Overlay Improvements
    • Plan preparation in progress
  • #24-08 2024 Crack Seal Improvements
    • Plan preparation in progress
  • #24-09 2024 Pavement Rejuvenator Improvements
    • Plan preparation in progress
  • #24-11 Alpine Drive MSA Street Reconstruction (Puma St to CSAH 83)
    • Plan preparation in progress
    • SFDR design (AET)
  • #24-12 Juniper Woods 1st – 3rd Street Reconstruction
    • Plan preparation in progress
  • #23-01 161st Avenue Reconstruction
    • Final payment anticipated Spring 2024
  • #23-02 Central Park Parking Lot Reconstruction
    • Final payment anticipated Spring 2024
  • #23-04 167th Avenue Reconstruction
    • Final payment anticipated Spring 2024
  • #23-05 Barthel's Rum River Acres 2nd Reconstruction
    • Final payment anticipated Spring 2024
  • #23-10 Whispering Pines Estates Plat 3 Reconstructions
    • Final payment anticipated Spring 2024
  • #23-11 Trott Brook Crossing Sanitary Sewer Lift Station Improvements
    • Final payment anticipated Spring/Summer 2024
  • #23-12 HY-10 Ramsey Improvements
    • Final payment anticipated Spring 2024
  • #23-19 COR Infrastructure Improvements
    • Plans approximately 90% complete
    • City Council to consider approving plans and authorizing bids February 13, 2024
  • #23-20 COR Mass Grading
    • Approximately 90% complete
    • Completion anticipated Spring 2024
  • #22-17 Highway 47 Sound Wall north of Xkimo Street
    • MnDOT is preparing a Cooperative Construction Agreement
    • Staff anticipates requesting Council approval to authorize bids Spring 2024
  • #21-08 WTP Trunk Watermain Improvements
    • Construction start anticipated late March 2024
  • #21-09 Centralized Water Treatment Plant
    • Construction in progress
    • Substantial completion scheduled for May 1, 2025
    • Final completion scheduled for August 1, 2025
  • #20-11 Ramsey Gateway Highway 10 Improvements
    • Construction and building demo’s in progress
    • Final completion anticipated June 2026
 
City of Anoka Improvement Projects
  • Highway 47 Corridor Improvements
    • 3-lane design proposed south of Bunker Lake Boulevard
    • City received regional solicitation funds for 2027 construction
    • Signal system at McKinley Street is proposed to be permanent
    • Anoka webpage https://clients.bolton-menk.com/anokahwy47/
 
Anoka County Improvement Projects
  • 2024 Pavement Overlay Improvements
    • Portions of CSAH 83 and CR 27
    • City staff are reviewing final plans
    • No City funds requested
    • City Engineer to sign title sheet
 
MnDOT Improvement Projects  
Studies & Items of Interest
  • Commercial/Industrial/Residential Developments
    • Staff can respond to questions as needed  

Time Frame/Observations/Alternatives:

Staff estimates up to 10 minutes will be needed for updates and discussion.  

Recommendation:

N/A

Outcome/Action:

No formal action required.  For Committee review and discussion purposes only.  

Attachments

No file(s) attached.

Form Review

Inbox Reviewed By Date
Brian Hagen Brian Hagen 01/11/2024 11:03 AM
Form Started By:
Bruce Westby
Started On:
01/10/2024 03:04 PM
Final Approval Date:
01/11/2024