City Improvement Projects
#24-01 Barthel’s Rum River Acres & White Pine Estates Street Reconstructions
  • Bid opening February 21, 2024
  • CC to consider award of contract February 26, 2024
#24-02 Halls Dover Acres Street Reconstructions
  • Bid opening February 21, 2024
  • CC to consider award of contract February 26, 2024
#24-03 2024 NE Ramsey Street Reconstructions
  • Plan preparation in progress (Hakanson Anderson)
#24-04 180th Lane Drainage Improvements
  • Plan preparation in progress
  • Coordinating design with property owners, City of Nowthen and MnDOT
  • Anticipate requesting CC approval to advertise bids Spring/Summer 2024
#24-05 Xkimo St MSA (TH47 to 142nd Avenue) Reconstruction
  • Plan preparation in progress (Hakanson Anderson)
#24-06 2024 MSA Pavement Overlay Improvements (McKinley St)
  • Plan preparation in progress
#24-07 2024 Neighborhood Overlay Improvements
  • Plan preparation in progress
#24-08 2024 Crack Seal Improvements
  • Bid opening March 4, 2024
#24-09 2024 Pavement Rejuvenator Improvements
  • Plan preparation in progress
#24-11 Alpine Drive MSA Street Reconstruction (Puma St to CSAH 83)
  • Bid opening March 20, 2024
  • CC to consider award of contract March 26, 2024
#24-12 Juniper Woods 1st – 3rd Street Reconstructions
  • Bid opening March 4, 2024
  • CC to consider award of contract March 12, 2024
#24-51 TH 47 Trail Gap Connection – 142nd Avenue to Xkimo Street (NEW)
  • Bolton & Menk preparing plans and specs for 10’ trail construction
  • Solicitation of Request for Quotes for construction anticipated Spring 2024
#23-01 161st Avenue Reconstruction
  • Final payment anticipated Spring 2024
#23-02 Central Park Parking Lot Reconstruction
  • Final payment anticipated Spring 2024
#23-04 167th Avenue Reconstruction
  • Final payment anticipated Spring 2024
#23-05 Barthels Rum River Acres 2nd Street Reconstructions
  • Final payment anticipated Spring 2024
#23-10 Whispering Pines Estates Plat 3 Street Reconstructions
  • Final payment anticipated Spring 2024
#23-11 Trott Brook Crossing Sanitary Sewer Lift Station Improvements
  • CC to consider final payment February 26, 2024
#23-12 HY-10 Ramsey Improvements
  • CC to consider final payment February 26, 2024
#23-19 COR Infrastructure Improvements
  • Bid opening March 13, 2024
  • CC to consider award of contract March 26, 2024
#23-20 COR Mass Grading
  • Substantially complete
  • Working to correct leaks in pond lining in 4 locations
  • Final completion anticipated Spring 2024
#22-17 Highway 47 Sound Wall north of Xkimo Street
  • MnDOT preparing Cooperative Construction Agreement
  • CC anticipated to consider authorizing bids Spring/Summer 2024
#21-08 WTP Trunk Watermain Improvements
  • Preconstruction meeting scheduled for March 26, 2024
  • Includes reconstruction of 143rd Avenue
#21-09 Centralized Water Treatment Plant
  • Construction on schedule for substantial completion May 1, 2025
  • Final completion scheduled for August 1, 2025
#20-11 Ramsey Gateway Highway 10 Improvements  
City of Anoka Improvement Projects
Highway 47 Corridor Improvements
  • 3-lane design proposed south of Bunker Lake Boulevard
  • City received regional solicitation funds for 2027 construction
  • Signal system at McKinley Street proposed to be permanent
  • Anoka webpage https://clients.bolton-menk.com/anokahwy47/
 
Anoka County Improvement Projects
2024 Pavement Overlay Improvements
  • Portions of CSAH 83 and CR 27 will receive pavement overlays in 2024
  • Staff reviewed plans and City Engineer signed title sheet for CSAH 83 plans
 
MnDOT Improvement Projects
Anoka Solution Highway 10 Improvements
  • Final completion Spring 2024
US 10 / 169 & Ferry Street / TH 47 Interchange
  • Final completion Spring 2024
Ferry Street / Trunk Highway 47 Grade Separation @ BNSF Rail Crossing  
Studies & Items of Interest
Commercial/Industrial/Residential Developments
Staff can respond to questions as needed  

Time Frame/Observations/Alternatives:

Staff estimates up to 10 minutes will be needed for updates and discussion.  

Recommendation:

Dependent on discussions.

Outcome/Action:

No formal action required.  For Committee review and discussion purposes only.  

Attachments

No file(s) attached.

Form Review

Inbox Reviewed By Date
Brian Hagen Brian Hagen 02/15/2024 01:08 PM
Form Started By:
Bruce Westby
Started On:
02/14/2024 05:22 PM
Final Approval Date:
02/15/2024