6.1.
| Public Works Committee |
| Meeting Date: | 02/20/2024 |
| Primary Strategic Plan Initiative: | {ud_pd8} |
Title:
Receive Updates on Improvement Projects, Studies and Items of Interest
Purpose/Background:
The purpose of this case is to update the Public Works Committee on current and proposed City, County and MnDOT improvement projects and studies, and on other items of interest to the Committee.
City Improvement Projects
#24-01 Barthel’s Rum River Acres & White Pine Estates Street Reconstructions
City of Anoka Improvement Projects
Highway 47 Corridor Improvements
Anoka County Improvement Projects
2024 Pavement Overlay Improvements
MnDOT Improvement Projects
Anoka Solution Highway 10 Improvements
Studies & Items of Interest
Commercial/Industrial/Residential Developments
Staff can respond to questions as needed
City Improvement Projects
#24-01 Barthel’s Rum River Acres & White Pine Estates Street Reconstructions
- Bid opening February 21, 2024
- CC to consider award of contract February 26, 2024
- Bid opening February 21, 2024
- CC to consider award of contract February 26, 2024
- Plan preparation in progress (Hakanson Anderson)
- Plan preparation in progress
- Coordinating design with property owners, City of Nowthen and MnDOT
- Anticipate requesting CC approval to advertise bids Spring/Summer 2024
- Plan preparation in progress (Hakanson Anderson)
- Plan preparation in progress
- Plan preparation in progress
- Bid opening March 4, 2024
- Plan preparation in progress
- Bid opening March 20, 2024
- CC to consider award of contract March 26, 2024
- Bid opening March 4, 2024
- CC to consider award of contract March 12, 2024
- Bolton & Menk preparing plans and specs for 10’ trail construction
- Solicitation of Request for Quotes for construction anticipated Spring 2024
- Final payment anticipated Spring 2024
- Final payment anticipated Spring 2024
- Final payment anticipated Spring 2024
- Final payment anticipated Spring 2024
- Final payment anticipated Spring 2024
- CC to consider final payment February 26, 2024
- CC to consider final payment February 26, 2024
- Bid opening March 13, 2024
- CC to consider award of contract March 26, 2024
- Substantially complete
- Working to correct leaks in pond lining in 4 locations
- Final completion anticipated Spring 2024
- MnDOT preparing Cooperative Construction Agreement
- CC anticipated to consider authorizing bids Spring/Summer 2024
- Preconstruction meeting scheduled for March 26, 2024
- Includes reconstruction of 143rd Avenue
- Construction on schedule for substantial completion May 1, 2025
- Final completion scheduled for August 1, 2025
- Construction in progress
- Final completion anticipated June 2026
- Project webpage https://www.anokacountymn.gov/3918/Hwy-10Ramsey-Blvd-Interchange
City of Anoka Improvement Projects
Highway 47 Corridor Improvements
- 3-lane design proposed south of Bunker Lake Boulevard
- City received regional solicitation funds for 2027 construction
- Signal system at McKinley Street proposed to be permanent
- Anoka webpage https://clients.bolton-menk.com/anokahwy47/
Anoka County Improvement Projects
2024 Pavement Overlay Improvements
- Portions of CSAH 83 and CR 27 will receive pavement overlays in 2024
- Staff reviewed plans and City Engineer signed title sheet for CSAH 83 plans
MnDOT Improvement Projects
Anoka Solution Highway 10 Improvements
- Final completion Spring 2024
- Final completion Spring 2024
- Preliminary design suspended; exploring S-curve realignment and stormwater impacts
- $45M in bonds authorized October 2020
- Construction proposed for 2024 to 2026, depending on final design
- MnDOT webpage http://www.dot.state.mn.us/metro/projects/hwy47rr-anoka/
Studies & Items of Interest
Commercial/Industrial/Residential Developments
Staff can respond to questions as needed
Time Frame/Observations/Alternatives:
Staff estimates up to 10 minutes will be needed for updates and discussion.
Recommendation:
Dependent on discussions.
Outcome/Action:
No formal action required. For Committee review and discussion purposes only.
Attachments
No file(s) attached.
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Brian Hagen | Brian Hagen | 02/15/2024 01:08 PM |
- Form Started By:
- Bruce Westby
- Started On:
- 02/14/2024 05:22 PM
- Final Approval Date:
- 02/15/2024