7.4.
CC Regular Session
Meeting Date: 05/14/2024
   
Primary Strategic Plan Initiative: {ud_pd8}

Information

Title:

Adopt Resolution #24-131 Accepting Bids, Awarding Contract and Authorizing Funding for Improvement Project #24-54, The Waterfront 

Purpose/Background:

Background
As part of the city's community park system, a water-centric park known as The Waterfront has been envisioned for more than a decade in Ramsey's downtown. In the Fall of 2023, the mass grading and establishment seeding for the park was completed.  At the Park & Commission's regular January 2024 meeting, the Commission recommended, and City Council subsequently approved, preparing plans and specifications and obtaining bids for the trail around the 7 acre pond and associated improvements, which included trees and site furnishings (benches, bike racks and trash receptacles with concrete pads).  The following were the preliminary project cost estimates:
 
  Estimate  
Grading, Trail and Boulder Wall $222,613
Trees (60)   $47,900
Concrete Flat Work $88,060
Furnishings   $33,700
Contingency (approx. 10%) $39,000
Construction Staking/Survey $15,000
  Total $446,273

Purpose
The purpose of this case is to award a contract for the construction of the trail and authorize the balance of funding for planting 60 trees and providing concrete pads, benches, trash receptacles and bike racks for the park. 

Time Frame/Observations/Alternatives:

Observations
Following authorization to obtain costs for the construction of the trails, trees and furnishings, the aforementioned Ad for Bid and Requests for Quotations were issued—and the following actual costs were determined to complete the park project in the Summer of 2024.
 
  Estimate       Actual  
Grading, Trail and Boulder Wall $222,613   Grading, Trail and Boulder Wall $169,165
Trees (60)   $47,900   Trees (60)   $32,730
Concrete Flat Work $88,060   Concrete Flat Work $66,320
Furnishings   $33,700   Furnishings   $33,700
Contingency (approx. 10%) $39,000   Contingency (approx. 10%) $30,000
Construction Staking/Survey $15,000   Construction Staking/Survey $13,844
  Total $446,273     Total $345,759

Alternatives
Alternatives include:
1) Not proceeding with park improvements at this time.
2) Proceeding with park improvements as identified.
3) Some other unspecified option.

Additional information will be available at the meeting.
  

Funding Source:

The funding for Improvement Project #24-54, The Waterfront, would be from the Park Trust Fund, which has a present balance of >$7M.  

Recommendation:

On March 14th 2024, the Park & Recreation Commission recommended to City Council up to $430,000 in funding from the Park Trust Fund for the improvements Resolution #24-131 and this case discusses for The Waterfront.

Outcome/Action:

Motion to Adopt Resolution #24-131 Accepting Bids, Awarding Contract and Authorizing Funding for Improvement Project #24-54, The Waterfront  

Attachments

Form Review

Inbox Reviewed By Date
Bruce Westby Bruce Westby 05/09/2024 12:47 PM
Brian Hagen Brian Hagen 05/09/2024 03:16 PM
Form Started By:
Mark Riverblood
Started On:
05/07/2024 08:04 AM
Final Approval Date:
05/09/2024