Title
Adopt Resolution #24-161 Approving Partial Payment to Northdale Construction Co. Inc. for Improvement Project #21-08, WTP Trunk Watermain Improvements.
Purpose/Background:
Resolution and Pay Request attached.
Recommendation:
The Senior Engineering Technician has inspected the completed work and recommends partial payment to Northdale Construction Co. Inc. for improvement project #21-08, WTP Trunk Watermain Improvements in the amount of $2,136,706.33.
Action:
Motion to adopt Resolution #24-161 approving partial payment to Northdale Construction Co. Inc. for improvement project #21-08, WTP Trunk Watermain Improvements in the amount of $2,136,706.33.
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Bruce Westby | Bruce Westby | 06/20/2024 11:25 AM |
| Brian Hagen | Kathy Schmitz | 06/20/2024 03:27 PM |
- Form Started By:
- Stacie Damjanovich
- Started On:
- 06/06/2024 01:20 PM
- Final Approval Date:
- 06/20/2024