6.1.
| Public Works Committee |
| Meeting Date: | 06/18/2024 |
| Primary Strategic Plan Initiative: | {ud_pd8} |
Title:
Receive Updates on Improvement Projects, Studies and Items of Interest
Purpose/Background:
The purpose of this case is to update the Public Works Committee on current and proposed City, County and MnDOT improvement projects and studies, and on other items of interest to the Committee.
City Improvement Projects
#24-01 Barthel’s Rum River Acres & White Pine Estates Street Reconstructions#24-08 2024 Crack Seal Improvements
City of Anoka Improvement Projects
Highway 47 Corridor Improvements
Anoka County Improvement Projects
2024 Pavement Overlay Improvements
MnDOT Improvement Projects
Anoka Solution Highway 10 Improvements
US 10 / 169 & Ferry Street / TH 47 Interchange
Studies & Items of Interest
Wetland 114 P staff updates – Staff will present information on the following during the meeting
Staff can respond to questions as needed.
City Improvement Projects
#24-01 Barthel’s Rum River Acres & White Pine Estates Street Reconstructions
- Construction in progress
- Substantial completion scheduled for August 2, 2024
- Construction in progress
- Substantial completion scheduled for August 2, 2024
- Executing contracts
- Preconstruction meeting held on June 14th
- Substantial completion scheduled for September 30, 2024
- Anoka County Union Herald did not advertise bids as requested è bids delayed 2 weeks
- Bids will be publicly opened July 15th
- Substantial completion scheduled for August 31, 2024
- Preconstruction meeting held on June 14th
- Substantial completion scheduled for September 1, 2024
- Plan preparation in progress
- Construction proposed for Summer/Fall 2024
- Executing contracts and scheduling preconstruction meeting
- Substantial completion scheduled for August 31, 2024
Construction complete
- Construction proposed for Summer 2024
- Final completion scheduled for August 3, 2024
- Construction in progress
- Substantial completion scheduled for August 2, 2024
- Construction in progress
- Substantial completion scheduled for August 2, 2024
- Bolton & Menk preparing plans and specs for 10’ trail construction
- Request for Quotes anticipated Spring 2024
- Final payment anticipated July 2024
- Final payment anticipated July 2024
- Final payment anticipated July 2024
- Final payment anticipated July 2024
- Final payment anticipated July 2024
- Construction in progress
- Construction completion anticipated late August 2024
- Monitoring corrected leaks in pond lining
- Final completion anticipated July 2024
- MnDOT executing Cooperative Construction Agreement #1056358
- Bids will be publicly opened July 1st
- Substantial completion scheduled for August 31, 2024
- Construction in progress
- 143rd Avenue watermain construction and street reconstruction proposed to start late June
- Substantial completion anticipated August 2024
- Construction in progress
- Substantial completion scheduled for May 1, 2025
- Final completion scheduled for August 1, 2025
- Construction in progress
- Final completion anticipated June 2026
- Project webpage https://www.anokacountymn.gov/3918/Hwy-10Ramsey-Blvd-Interchange
City of Anoka Improvement Projects
Highway 47 Corridor Improvements
- 3-lane design proposed south of Bunker Lake Boulevard
- City received regional solicitation funds for 2027 construction
- Signal system at McKinley Street proposed to be permanent
- Project webpage https://clients.bolton-menk.com/anokahwy47/
Anoka County Improvement Projects
2024 Pavement Overlay Improvements
- CSAH 83 (173rd to 181st) and CR 27 (Hwy 47 to CSAH 7)
- Work tentatively scheduled from early August through late September
- Project webpage https://www.anokacountymn.gov/4070/2024-Projects
MnDOT Improvement Projects
Final completion Spring 2024
Final completion Spring 2024
- Preliminary design officially paused to explore S-curve realignment and stormwater impacts
- $45M in bonds authorized October 2020
- MnDOT webpage http://www.dot.state.mn.us/metro/projects/hwy47rr-anoka/
Studies & Items of Interest
Wetland 114 P staff updates – Staff will present information on the following during the meeting
- Observed water levels this Spring
- Public comments, complaints and concerns received this Spring
Staff can respond to questions as needed.
Notification:
Notifications are not required for this case.
Time Frame/Observations/Alternatives:
Staff estimates up to 20 minutes will be needed for updates and discussion.
Recommendation:
Staff will offer recommendations on specific items when requested.
Outcome/Action:
No formal action required. For Committee review and discussion purposes only.
Attachments
No file(s) attached.
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Brian Hagen | Brian Hagen | 06/13/2024 01:24 PM |
- Form Started By:
- Bruce Westby
- Started On:
- 06/13/2024 07:54 AM
- Final Approval Date:
- 06/13/2024