Receive Updates on Improvement Projects, Studies and Items of Interest
Purpose/Background:
The purpose of this case is to update the Public Works Committee on current and proposed City, County and MnDOT improvement projects and studies, and on other items of interest to the Committee.
City Improvement Projects
#24-01 Barthel’s Rum River Acres & White Pine Estates Street Reconstructions
City of Anoka Improvement Projects
Highway 47 Corridor Improvements
Anoka County Improvement Projects
2024 Pavement Overlay Improvements
MnDOT Improvement Projects
Ferry Street / Trunk Highway 47 Grade Separation @ BNSF Rail Crossing
Studies & Items of Interest
Wetland 114 P staff updates
PWC Future Topics Calendar Discussion Items
No updates.
City Improvement Projects
#24-01 Barthel’s Rum River Acres & White Pine Estates Street Reconstructions
- Construction in progress
- Substantial completion scheduled for August 2, 2024
- Construction in progress
- Substantial completion scheduled for August 2, 2024
- Construction in progress
- Substantial completion scheduled for September 30, 2024
- Anoka County Union Herald did not advertise bids as requested è bids delayed 2 weeks
- Bids publicly opened July 15th
- Substantial completion scheduled for August 31, 2024
- Construction in progress.
- Substantial completion scheduled for September 1, 2024
- Bids will be publicly opened August 5, 2024
- Substantial completion scheduled for October 11, 2024
- Final completion scheduled for June 30, 2025
- Construction in progress
- Substantial completion scheduled for August 31, 2024
- Preconstruction meeting scheduled for July 18, 2024
- Final completion is anticipated to occur by August 30, 2024
- Final completion scheduled for August 3, 2024
- Construction in progress
- Substantial completion scheduled for August 2, 2024
- Construction in progress
- Substantial completion scheduled for August 2, 2024
- Bolton & Menk preparing plans and specs for 10’ trail construction
- Request for Quotes anticipated Summer 2024
- Final payment anticipated July 2024
- Final payment anticipated July 2024
- Final payment anticipated July 2024
- Final payment anticipated July 2024
- Final payment anticipated July 2024
- Construction in progress
- Construction completion anticipated late August 2024
- Pond lining leaks have been repaired
- Final completion anticipated July/August 2024
- Execution of contracts in progress
- Substantial completion scheduled for August 31, 2024
- Construction in progress
- 143rd Avenue restricted to one-way traffic (Westbound only)
- Substantial completion anticipated September 13, 2024
- Construction in progress
- Substantial completion scheduled for May 1, 2025
- Final completion scheduled for August 1, 2025
- Construction in progress
- Final completion anticipated June 2026
- Project webpage https://www.anokacountymn.gov/3918/Hwy-10Ramsey-Blvd-Interchange
City of Anoka Improvement Projects
Highway 47 Corridor Improvements
- 3-lane design proposed south of Bunker Lake Boulevard
- City received regional solicitation funds for 2027 construction
- Signal system at McKinley Street proposed to be permanent
- Project webpage https://clients.bolton-menk.com/anokahwy47/
Anoka County Improvement Projects
2024 Pavement Overlay Improvements
- CSAH 83 (173rd to 181st) and CR 27 (Hwy 47 to CSAH 7)
- Work tentatively scheduled from early August through late September
- Project webpage https://www.anokacountymn.gov/4070/2024-Projects
MnDOT Improvement Projects
Ferry Street / Trunk Highway 47 Grade Separation @ BNSF Rail Crossing
- Preliminary design officially paused to explore S-curve realignment and stormwater impacts
- $45M in bonds authorized October 2020
- MnDOT webpage http://www.dot.state.mn.us/metro/projects/hwy47rr-anoka/
Studies & Items of Interest
Wetland 114 P staff updates
- See separate case
- Staff can respond to questions as needed.
PWC Future Topics Calendar Discussion Items
No updates.
Notification:
N/A
Time Frame/Observations/Alternatives:
Staff estimates up to 15 minutes will be needed for updates and discussion.
Funding Source:
N/A
Recommendation:
Staff will offer recommendations on specific items when requested.
Outcome/Action:
No formal action required. For Committee review and discussion purposes only.
Attachments
No file(s) attached.
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Brian Hagen | Brian Hagen | 07/11/2024 11:54 AM |
- Form Started By:
- Bruce Westby
- Started On:
- 07/09/2024 04:30 PM
- Final Approval Date:
- 07/11/2024