- Meeting Date:
- 01/24/2012
- By:
- Tim Himmer, Engineering/Public Works
Information
Title:
Background:
The project includes the realignment of Sunwood Drive, between approximately Zeolite Street and Armstrong Boulevard (see attached preliminary design). The intent is to work north to south on Armstrong Boulevard and complete another section of the roadway in its final location; to set the stage for the ultimate interchange over the railroad tracks and TH 10. It will also create additional developable land for retail space near the new intersection, and create a signalized full access to the COR from Armstrong Boulevard.
Draft feasibility studies were presented to the Public Works Committee and HRA on December 13, 2011, with the only remaining outstanding item being the funding package. On that date the HRA authorized the preparation of appraisals for the potential acquisition of 3 parcels along the west side of Armstrong Boulevard that are necessary for portions of this project, and ultimately the interchange project. This case provides the final draft of the feasibility studies and includes a funding package for the entire project.
Observations:
Recall that there are a few design items contained in these feasibility studies that differ slightly from the preliminary design of the Armstrong/TH 10 interchange project. Those discrepancies were discussed by the City Council in work session on December 13, 2011 and following is the direction received:
- The location of 147th Avenue NW is currently shown in its existing location on the interchange design, but it is shifted slightly south of its current location in the Sunwood realignment project. This was done to improve the primary access into the COR from Armstrong Boulevard, and be consistent with the HRA approved development plan. Council felt we should continue with the design shown for the Sunwood realignment, as the HRA would be undertaking a process to acquire the necessary land along the west side of Armstrong Boulevard. It was also explained that current Anoka County policy requires the City to own and maintain the signal proposed at this intersection in perpetuity, based upon warrants.
- Armstrong Boulevard is shown to diverge to the east slightly, out of the existing right-of-way into the COR property on the interchange design, but remains in its current alignment on the Sunwood project. The interchange project was designed to avoid total takings of the properties along the west side of Armstrong, and therefore the roadway is proposed to move slightly east onto vacant HRA land in an effort to keep acquisition costs down. The Sunwood project proposes holding the existing Armstrong alignment, which is consistent with HRA direction to investigate purchasing properties on the west side of Armstrong in an attempt to solve right-of-way acquisition issues for both projects. If we are able to successfully acquire these parcels Armstrong would be able to remain in its current alignment, thereby resulting in improved roadway geometrics and reduced interchange costs.
- Staff was approached by Mid America, the property owner of Northstar Marketplace, requesting a right-in condition be included in the interchange project for better access to their site. Council expressed some concerns related to the proposed sketch but decided to delay an official response until Mid America could provide additional detailed information as to the feasibility of such an access. It was discussed that Mid America should perform the necessary investigations and analysis to determine whether this access could be accommodated, not only by the City but also the other jurisdictions involved (Anoka County and MnDOT), before a decision could be made on who would be responsible to pay for and maintain such an improvement.
- One final item of discussion on both projects was related to turf establishment. Council direction was to install the City's required topsoil and sod within all City right-of-way, but seed could be substituted in place of sod in the County right-of-way. It was proposed (and accepted) this way because portions of the Armstrong work will only be temporary until the interchange is constructed. The boulevard landscaping in these temporary areas can be included with development review, to ensure site landscaping accounts for these areas when develop occurs, and what isn't resolved through development can be incorporated into the interchange design.
Recommendation:
-and-
Staff is recommending award of design contracts for this project in an amount not to exceed $220,012 (Landform - $79,800, and WSB - $140,212).
One final item of note is that construction administration (surveying, staking, inspections, etc.) has not been included in any of the consultant proposals to date. Staff is currently awaiting proposals from both Landform and WSB, and will also be reviewing current workload to determine how best to accomplish this task. We may be in a position to make a recommendation at the Council meeting with regard to construction administration, or it may have to be brought forward at a subsequent meeting.
Funding Source:
A few funding scenarios to finance the project are attached for consideration, and staff is looking for direction on which option is preferred by the City Council. Once a final financing package is determined the feasibility studies can be finalized, consistent with that direction, and preparation of construction documents can commence.
A discussion to consider deviating from the existing policy on distribution of land sale proceeds is contemplated in this funding analysis. There are also a couple of grant opportunities, that staff is currently preparing applications for, which are included in the analysis. If we are successful in securing those grant dollars they could be included in the funding package in place of other options being considered.
Council Action:
Motion to approve the feasibility studies for the Sunwood realignment project, consistent with the chosen financing package.
-and-
Motion to award engineering design contracts in an amount not to exceed $220,012.
-and-
Motion to authorize the preparation of plans and specifications.
Attachments
- Sunwood Preliminary Layout
- Armstrong Preliminary Layout
- WSB Draft Feasibility Study
- Landform Draft Feasibility Study
- Funding Scenarios
- Landform Design Proposal
- WSB Design Proposal
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Kurt Ulrich | Kurt Ulrich | 01/19/2012 03:56 PM |
- Form Started By:
- thimmer
- Started On:
- 01/17/2012 01:28 PM
- Final Approval Date:
- 01/19/2012