6.9.
CC Regular Session New
Meeting Date: 08/27/2024
   
Primary Strategic Plan Initiative: {ud_pd8}

Title:

Adopt Resolution #23-221 Authorizing Partial Payment No. 14 to Magney Construction, Inc. for Improvement Project 21-09; Centralized Water Treatment Plant.

Purpose/Background:

Pay Estimate and Resolution attached.

Recommendation:

The Resident Project Representative from Advanced Engineering and Environmental Services (AE2S) has inspected the completed work and recommends partial payment #14 to Magney Construction, Inc. for Improvement Project 21-09, Centralized Water Treatment Plant, in the amount of $1,023,085.54.

Outcome/Action:

Adopt Resolution #24-221 authorizing partial payment #14 to Magney Construction, Inc. of Chanhassen, Minnesota, for Improvement Project #21-09, Centralized  Water Treatment Plant, in the amount of $1,023,085.54.

Attachments

Form Review

Inbox Reviewed By Date
Bruce Westby Bruce Westby 08/19/2024 01:08 PM
Brian Hagen Brian Hagen 08/22/2024 08:34 AM
Form Started By:
Marsha Weidner
Started On:
08/08/2024 01:05 PM
Final Approval Date:
08/22/2024