6.6.
| CC Regular Session |
| Meeting Date: | 10/22/2024 |
| Primary Strategic Plan Initiative: | {ud_pd4} |
Title:
Adopt Resolution #24-290 Approving Change Order No. 26 for Improvement Project #20-11, Ramsey Gateway Highway 10 Improvements
Purpose/Background:
The existing watermain on McKinley Street West of Sunfish Lake Boulevard runs between proposed sanitary sewer manhole 24 and existing sanitary sewer manhole 250 and conflicts with the proposed excavation and sanitary sewer work. Additionally, the excavation limits required to remove and replace sanitary sewer manhole 24 per the original plan conflicts with existing sanitary sewer manhole 250 that is to remain in place. The Contractor must therefore remove and replace approximately 400-feet of watermain, along with curb and gutter and bituminous pavement required to reconstruct an additional 400-feet of McKinley Street West of Sunfish Lake Boulevard. Additionally, the alignment and location of sanitary sewer manhole 24 must be revised to resolve the conflict with existing sanitary sewer manhole 250.
This work is estimated to cost $78,766.86. Payment for the extra work will be made at contract unit prices and a lump sum payment that will include all costs for additional dewatering, sanitary sewer bypass pumping, and mobilization. Additionally, the Plan (P) Quantity for Aggregate Base Cl 6 is increased in this Change Order as required to reconstruct the additional 400-feet of McKinley Street. Payment for this work will be covered under the City's $4M lump sum contribution per the executed Joint Powers Agreement.
This change does not impact contract time.
This work is estimated to cost $78,766.86. Payment for the extra work will be made at contract unit prices and a lump sum payment that will include all costs for additional dewatering, sanitary sewer bypass pumping, and mobilization. Additionally, the Plan (P) Quantity for Aggregate Base Cl 6 is increased in this Change Order as required to reconstruct the additional 400-feet of McKinley Street. Payment for this work will be covered under the City's $4M lump sum contribution per the executed Joint Powers Agreement.
This change does not impact contract time.
Recommendation:
The MnDOT Project Engineer and City of Ramsey staff have reviewed and approve of the costs associated with this change.
Outcome/Action:
Adopt Resolution #24-290 approving Change Order No. 26 for Improvement Project #20-11, Ramsey Gateway Highway 10 Improvements.
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Brian Hagen | Brian Hagen | 10/17/2024 02:24 PM |
- Form Started By:
- Bruce Westby
- Started On:
- 10/04/2024 11:07 AM
- Final Approval Date:
- 10/17/2024