6.9.
| CC Regular Session |
| Meeting Date: | 11/26/2024 |
| Primary Strategic Plan Initiative: | {ud_pd8} |
Title:
Adopt Resolution #24-320 Authorizing Partial Payment #17 to Magney Construction, Inc. for Improvement Project #21-09; Centralized Water Treatment Plant.
Purpose/Background:
Pay Estimate and Resolution attached.
Recommendation:
The Resident Project Representative from Advanced Engineering and Environmental Services (AE2S) has inspected the completed work and recommends partial payment #17 to Magney Construction, Inc. for said project in the amount of $803,273.27.
Outcome/Action:
Adopt Resolution #24-320, authorizing partial payment #17 to Magney Construction, Inc., of Chanhassen, Minnesota; for Improvement Project #21-09, Centrailized Water Treatment Plant, in the amount of $803,273.27.
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Bruce Westby | Bruce Westby | 11/20/2024 10:11 AM |
| Bruce Westby | Bruce Westby | 11/21/2024 01:04 PM |
| Brian Hagen | Brian Hagen | 11/21/2024 02:38 PM |
- Form Started By:
- Marsha Weidner
- Started On:
- 11/07/2024 03:17 PM
- Final Approval Date:
- 11/21/2024