Receive Updates on Improvement Projects, Studies and Items of Interest

Purpose/Background:

The purpose of this case is to update the Public Works Committee on current and proposed City, County and MnDOT improvement projects and studies, and on other items of interest to the Committee.

City Improvement Projects
#25-01 Rivers Bend Regional Stormwater Pond Improvements
  • Construction in progress
  • External funding updates
  • Substantial completion scheduled for November 22, 2024
#25-02 MSA Sunwood Drive Reconstruction – CSAH 5 to Erkium Street
  • Design and plan preparation in progress
  • 2025 construction
#25-03 MSA Alpine Drive Reconstruction – CSAH 57 to TH 47
  • Design and plan preparation in progress
  • 2025 construction
#25-04 Dickenson’s Mississippi Estate Street Reconstruction
  • Design and plan preparation in progress
  • 2025 construction
#25-05 High Point Street Reconstruction
  • Design and plan preparation in progress
  • 2025 construction
#25-06 Sorteberg’s Street Reconstruction
  • Design and plan preparation in progress
  • 2025 construction
#24-01 Barthel’s Rum River Acres & White Pine Estates Street Reconstructions
  • Substantially complete
  • Punch list items are being addressed
#24-02 Halls Dover Acres Street Reconstruction
  • Substantially complete
  • Punch list items are being addressed
#24-03 2024 NE Ramsey Street Reconstruction
  • Substantially complete
  • Punch list items are being addressed
#24-04 Ford Brook Estates Drainage Improvements
  • Substantially complete
  • Punch list items are being addressed
#24-05 Xkimo St MSA (TH47 to 142nd Avenue) Reconstruction
  • Substantially complete
  • Punch list items are being addressed
#24-06 2024 MSA Pavement Overlay Improvements (McKinley St)
  • Substantially complete
  • Punch list items are being addressed
  • Final completion scheduled for June 30, 2025
#24-07 2024 Neighborhood Overlay Improvements
  • Substantially complete
  • Punch list items are being addressed
#24-09 2024 Pavement Rejuvenator Improvements
  • Substantially complete
  • Punch list items are being addressed
#24-10 2024 MSA Pavement Markings
  • Substantially complete
  • Punch list items are being addressed
#24-11 Alpine Drive MSA Street Reconstruction (Puma St to CSAH 83)
  • Substantially complete
  • Punch list items are being addressed
#24-12 Juniper Woods 1st – 3rd Street Reconstruction
  • Substantially complete
  • Punch list items are being addressed
#24-13 Fox Ridge Estates 1st and 2nd Additions Street Reconstruction
  • CC approved plans and authorized bids November 12th  
  • Advertisements published in Anoka Co Union Herald November 15th and 22nd
  • 2025 construction proposed
#24-14 Ramsey Gateway Mississippi River Outfall Removal
  • 2025 Change Order to IP #20-11, Ramsey Gateway Highway 10 Improvements
#24-51 TH 47 Trail Gap Connection – 142nd Avenue to Xkimo Street
  • Bolton & Menk prepared plans and specs for 10’ trail construction
  • MnDOT cost contribution update will be provided in November
#24-54 Waterfront Trail Improvements
  • Substantially complete
  • Punch list items are being addressed
#24-56 Lift Station #1 Generator Improvements
  • Substantial completion anticipated by end of November
#23-05 Barthel Rum River Acres 2nd Street Reconstruction
  • Substantially complete
  • Punch list items are being addressed
#23-19 COR Infrastructure Improvements
  • Substantially complete
  • Punch list items are being addressed
#23-20 COR Mass Grading
  • Final payment anticipated in November
#21-08 WTP Trunk Watermain Improvements
  • Substantially complete
  • Punch list items are being addressed
#21-09 Centralized Water Treatment Plant
  • Construction in progress
  • Substantial completion scheduled for August, 2025
  • Final completion scheduled for October, 2025
#20-11 Ramsey Gateway Highway 10 Improvements  
City of Anoka Improvement Projects
Ferry Street / Trunk Highway 47 Grade Separation of BNSF Rail Crossing 
  • City is leading project
  • $45M in bonds authorized October 2020
Highway 47 Corridor Improvements – Garfield St to Bunker Lk Blvd
  • Combining with above City-led project
  • 3-lane design
  • Received regional solicitation funds for 2027 construction
  • Permanent signal system at McKinley Street
  • Construction proposed for 2027 - 2029
 
Anoka County Improvement Projects
N/A
 
MnDOT Improvement Projects
N/A
 
Studies & Items of Interest
Wetland 114 P staff updates
  • Water levels stabilized
  • Staff continues to monitor water levels and will provide updates as needed
Commercial/Industrial/Residential Developments
  • Staff can respond to questions as needed. 
 
PWC Future Topics Calendar Discussion Items
GREP updates will be presented in January with detailed cost estimates and priority recommendations.   

Notification:

Notification is not required for this case.

Time Frame/Observations/Alternatives:

Staff estimates up to 10 minutes will be needed for updates and discussion.  

Recommendation:

Staff will offer recommendations on specific items when requested.  

Outcome/Action:

No formal action required.  For Committee review and discussion purposes only.  

Attachments

No file(s) attached.

Form Review

Inbox Reviewed By Date
Brian Hagen Brian Hagen 11/14/2024 03:16 PM
Form Started By:
Bruce Westby
Started On:
11/13/2024 02:13 PM
Final Approval Date:
11/14/2024