6.1.
| Public Works Committee |
| Meeting Date: | 01/21/2025 |
| Primary Strategic Plan Initiative: | {ud_pd8} |
Title:
Receive Updates on Improvement Projects, Studies and Items of Interest
Purpose/Background:
The purpose of this case is to update the Public Works Committee on current and proposed City, County and MnDOT improvement projects and studies, and on other items of interest to the Committee.
City Improvement Projects
#25-01 Rivers Bend Regional Stormwater Pond Improvements
City of Anoka Improvement Projects
Ferry Street / Trunk Highway 47 Grade Separation of BNSF Rail Crossing
Anoka County Improvement Projects
MnDOT Improvement Projects
Studies & Items of Interest
Wetland 114 P staff updates
PWC Future Topics Calendar Discussion Items
See calendar in next case.
City Improvement Projects
#25-01 Rivers Bend Regional Stormwater Pond Improvements
- Construction completed
- Receive first grant payment from the Anoka Conservation District (ACD) in December in the amount of $168,874.49.
- The second grant payment will be requested in late January after the next pay application is received.
- Project close out scheduled for Spring 2025
- 2025 construction
- See separate bid award case
- Design and plan preparation in progress
- 2025 construction
- Design and plan preparation in progress
- 2025 construction
- Design and plan preparation in progress
- 2025 construction
- See separate design alternative case
- Design and plan preparation in progress
- 2025 construction
- 2025 construction
- See separate bid authorization case
- 2025 construction
- See separate bid authorization case
- Substantially complete
- Punch list items are being addressed
- Substantially complete
- Punch list items are being addressed
- Substantially complete
- Punch list items are being addressed
- Substantially complete
- Punch list items are being addressed
- Substantially complete
- Punch list items are being addressed
- Substantially complete
- Punch list items are being addressed
- Final completion scheduled for June 30, 2025
- Substantially complete
- Punch list items are being addressed
- Substantially complete
- Punch list items are being addressed
- Substantially complete
- Punch list items are being addressed
- 2024 skim patching completed
- 2025 reconstruction
- See separate bid award case
- 2025 Change Order to IP #20-11, Ramsey Gateway Highway 10 Improvements
- Bolton & Menk prepared plans and specs for 10’ trail construction
- MnDOT cost contribution update is anticipated to be available in February
- Generator installation anticipated mid-January
- Construction complete
- Punch list items are being addressed
- Construction complete
- Final payment in progress
- Construction complete
- Punch list items are being addressed
- Construction in progress
- Substantial completion scheduled in August, 2025
- Final completion scheduled for October, 2025
- Sunfish Lake Blvd grade separations (RR and TH10) are complete and open to traffic
- Ramsey Blvd grade separations (RR and TH10) will be constructed in 2025
- Final completion anticipated June 2026
- Project webpage https://www.anokacountymn.gov/3918/Hwy-10Ramsey-Blvd-Interchange
City of Anoka Improvement Projects
Ferry Street / Trunk Highway 47 Grade Separation of BNSF Rail Crossing
- City is leading project
- $45M in bonds authorized October 2020
- Combined with above City-led project
- 3-lane design
- Received regional solicitation funds for 2027 construction
- Permanent signal system at McKinley Street
- Construction proposed for 2027 - 2029
Anoka County Improvement Projects
- No updates.
MnDOT Improvement Projects
- No updates.
Studies & Items of Interest
Wetland 114 P staff updates
- Water levels are stable.
- Staff continues to monitor water levels and will provide updates as needed.
- Staff can respond to questions as needed.
PWC Future Topics Calendar Discussion Items
See calendar in next case.
Notification:
Notification is not required for this case.
Time Frame/Observations/Alternatives:
Staff estimates up to 10 minutes will be needed for updates and discussion.
Recommendation:
Staff will offer recommendations on specific items when requested.
Outcome/Action:
No formal action required. For Committee review and discussion purposes only.
Attachments
No file(s) attached.
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Brian Hagen | Brian Hagen | 01/16/2025 04:05 PM |
- Form Started By:
- Bruce Westby
- Started On:
- 01/15/2025 06:50 PM
- Final Approval Date:
- 01/16/2025