6.1.
Public Works Committee
Meeting Date: 05/20/2025
   
Primary Strategic Plan Initiative: {ud_pd8}

Title:

Receive Updates on Improvement Projects, Studies and Items of Interest

Purpose/Background:

The purpose of this case is to update the Public Works Committee on current and proposed City, County and MnDOT improvement projects and studies, and on other items of interest to the Committee.
 
City Improvement Projects
2026 Pavement Management Program Projects
  • Obtaining/reviewing topographic surveys, geotechnical evaluations and utility testing
#26-01 MSA Bunker Lake Boulevard Reconstruction
  • Preparing plans and specifications
  • 2026 construction
#25-01 Rivers Bend Regional Stormwater Pond Improvements
  • Construction complete
  • Project close out Summer 2025
#25-02 MSA Sunwood Drive Reconstruction – CSAH 5 to Erkium Street
  • Construction in progress
  • Substantial completion anticipated by May 30th 
#25-03 MSA Alpine Drive Reconstruction – CSAH 57 to TH 47
  • Bid opening May 21st
  • 2025 construction
#25-04 Dickenson’s Mississippi Estate Street Reconstruction
  • Executing contracts / scheduling preconstruction meeting
  • Construction anticipated to begin late June/early July
#25-05 High Point Street Reconstruction
  • Construction will commence soon
#25-06 Sortebergs Street Reconstruction
  • Construction scheduled to begin May 19th
#25-07 2025 Neighborhood Pavement Overlay Improvements
  • Bid opening May 21st
  • 2025 construction
#25-08 Sunwood Drive Crosswalk Repairs
  • See separate case
#25-09 2025 Crack Seal Improvements
  • Construction almost complete
#25-10 2025 Pavement Rejuvenation
  • 2025 construction
#25-11 2025 MSA Pavement Marking Improvements
  • 2025 construction
#25-12 COR Street Lighting Improvements
  • Obtaining estimate from Connexus to light Ramsey Parkway and intersections
#24-01 Barthel’s Rum River Acres & White Pine Estates Street Reconstructions
  • Substantially complete
  • Punch list items are being addressed
#24-02 Halls Dover Acres Street Reconstruction
  • Substantially complete
  • Punch list items are being addressed
#24-03 2024 NE Ramsey Street Reconstruction
  • Substantially complete
  • Punch list items are being addressed
#24-04 Ford Brook Estates Drainage Improvements
  • Substantially complete
  • Punch list items are being addressed
#24-05 Xkimo St MSA (TH47 to 142nd Avenue) Reconstruction
  • Substantially complete
  • Punch list items are being addressed
#24-07 2024 Neighborhood Overlay Improvements
  • Substantially complete
  • Punch list items are being addressed
#24-11 Alpine Drive MSA Street Reconstruction (Puma St to CSAH 83)
  • Substantially complete
  • Punch list items are being addressed
#24-13 Fox Ridge Estates 1st and 2nd Additions Street Reconstruction
  • Construction in progress
  • Substantial completion Summer 2025
#24-14 Ramsey Gateway Mississippi River Outfall Removal
  • 2025 construction
  • Change Order 34 to IP #20-11, Ramsey Gateway Highway 10 Improvements
#24-51 TH 47 Trail Gap Connection – 142nd Avenue to Xkimo Street
  • Bolton & Menk prepared plans and specs for 10’ trail construction
  • Meeting with MnDOT soon to discuss cost contribution and project schedule
#23-19 COR Infrastructure Improvements
  • Construction complete
  • Punch list items are being addressed
#23-20 COR Mass Grading
  • Construction complete
  • Waiting for seed to germinate before issuing final payment
#21-09 Centralized Water Treatment Plant
  • Construction in progress
  • Substantial completion October 15, 2025
  • Final completion December 31, 2025
#20-11 Ramsey Gateway Highway 10 Improvements  
City of Anoka Improvement Projects
Ferry Street (Trunk Highway 47) Grade Separation of BNSF Rail Crossing
  • City-led project
  • $45M in bonds authorized October 2020
  • 2028 construction anticipated
Highway 47 Corridor Improvements – Garfield St to Bunker Lk Blvd
  • Combined with above City-led project
  • 3-lane design
  • Received regional solicitation funds for 2027 construction
  • Permanent signal system at McKinley Street
  • Construction proposed for 2027 - 2029
 
Anoka County Improvement Projects
  • No updates.
 
MnDOT Improvement Projects
  • No updates.
 
Studies & Items of Interest
Wetland 114 P staff updates
  • Staff continues to monitor water levels. Will provide updates as applicable.
Commercial/Industrial/Residential Developments
  • Staff can respond to questions as needed. 
 
PWC Future Topics Calendar Discussion Items
See calendar in the next case. 

Notification:

Notification is not required.

Time Frame/Observations/Alternatives:

Staff estimates up to 10 minutes will be needed for updates and discussion.

Recommendation:

Staff can offer recommendations on specific items upon request. 

Outcome/Action:

No formal action required.  For Committee review and discussion purposes only.  

Attachments

No file(s) attached.

Form Review

Inbox Reviewed By Date
Brian Hagen Marsha Weidner 05/15/2025 02:56 PM
Form Started By:
Bruce Westby
Started On:
05/15/2025 12:06 PM
Final Approval Date:
05/15/2025