Adopt Resolution #25-147 Authorizing partial payment #24 to Magney Construction, Inc. for Improvement Project #21-09; Centralized Water Treatment Plant.
Purpose/Background:
Pay Estimate and Resolution attached.
Recommendation:
The Resident Project Representative from Advanced Engineering and Environmental Services (AE2S) has inspected the completed work and recommends partial payment #24 to Magney Construction, Inc. for said project in the amount of $1,375,667.45.
Outcome/Action:
Adopt Resolution 25-147, authorizing partial payment #24 to Magney Construction, Inc. for improvement project #21-09, Centralized Water Treatment Plant in the amount of $1,375,667.45.
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Bruce Westby | Bruce Westby | 06/17/2025 04:16 PM |
| Brian Hagen | Brian Hagen | 06/18/2025 09:23 AM |
- Form Started By:
- Marsha Weidner
- Started On:
- 06/17/2025 09:14 AM
- Final Approval Date:
- 06/18/2025