6.1.
Public Works Committee
Meeting Date: 07/15/2025
   
Primary Strategic Plan Initiative: {ud_pd8}

Title:

Receive Updates on Improvement Projects, Studies and Items of Interest 

Purpose/Background:

The purpose of this case is to update the Public Works Committee on current and proposed City, County and MnDOT improvement projects and studies, and on other items of interest to the Committee.
 
City Improvement Projects
#26-01 MSA Bunker Lake Boulevard Reconstruction #26-02 2026 MSA Pavement Overlay Improvements #26-03 Carol-Rose Acres & Sports Haven Reconstructions
  • Preparing plans and specifications
  • 2026 construction proposed
#26-04 Countryside Estates Reconstructions
  • Preparing plans and specifications
  • 2026 construction proposed
#26-05 Flintwood Hills 2nd & 3rd Reconstructions
  • Preparing plans and specifications
  • 2026 construction proposed
#26-06 Riverside West Reconstructions
  • Preparing plans and specifications
  • 2026 construction proposed
#26-07 Section 01 Unplatted (S. CR 27) Reconstructions
  • Preparing plans and specifications
  • 2026 construction proposed
#26-08 2026 Neighborhood Pavement Overlay Improvements
  • Preparing plans and specifications
  • 2026 construction proposed
#25-01 Rivers Bend Regional Stormwater Pond Improvements
  • Construction complete
  • Project close out Summer 2025
#25-02 MSA Sunwood Drive Reconstruction – CSAH 5 to Erkium Street
  • Construction complete
  • Punch list items are being addressed
#25-03 MSA Alpine Drive Reconstruction – CSAH 57 to TH 47 #25-04 Dickenson’s Mississippi Estate Street Reconstruction #25-05 High Point Street Reconstruction
  • Construction in progress
#25-06 Sortebergs Street Reconstruction
  • Construction complete
  • Punch list items are being addressed
#25-07 2025 Neighborhood Pavement Overlay Improvements #25-08 Sunwood Drive Crosswalk Repairs
  • Preparing plans and specifications
  • Pavement repairs east of Sapphire Street completed separately July 14 - 21
#25-09 2025 Crack Seal Improvements
  • Construction complete
  • Final payment soon
#25-10 2025 Pavement Rejuvenation
  • Preconstruction meeting with Corrective Asphalt Materials, LLC was held July 8th
  • Construction starting soon
#25-11 2025 MSA Pavement Marking Improvements
  • Construction started July 9th
#25-12 COR Street Lighting Improvements
  • Obtaining estimate from Connexus to light Ramsey Parkway and intersections only
  • Staff will present the proposed lighting plan during the meeting
#24-03 2024 NE Ramsey Street Reconstruction
  • Construction complete
  • Working on as-builts
#24-04 Ford Brook Estates Drainage Improvements #24-05 Xkimo St MSA (TH47 to 142nd Avenue) Reconstruction
  • Substantially complete
  • Punch list items are being addressed
  • Contractor proposes mill and overlay to address poor rideability
#24-07 2024 Neighborhood Overlay Improvements
  • Construction complete
  • Punch list items are being addressed
#24-11 Alpine Drive MSA Street Reconstruction (Puma St to CSAH 83) #24-13 Fox Ridge Estates 1st and 2nd Additions Street Reconstruction
  • Construction substantially complete
  • Punch list items are being addressed
#24-14 Ramsey Gateway Mississippi River Outfall Removal
  • Construction in progress
#24-51 TH 47 Trail Gap Connection – 142nd Avenue to Xkimo Street
  • Bolton & Menk prepared plans and specs for 10’ trail construction
  • Work continues with MnDOT to determine cost contributions and project schedule
#23-19 COR Infrastructure Improvements
  • Construction complete
  • Punch list items are being addressed
#23-20 COR Mass Grading
  • Construction complete
  • Working to ensure adequate seeding germination before issuing final payment
#21-09 Centralized Water Treatment Plant
  • Construction in progress
  • City Council tour anticipated early August
  • Working through Change Order #3 and Engineering Amendment #3 requests
  • Completion Fall/Winter 2025
#20-11 Ramsey Gateway Highway 10 Improvements
  • Sunfish Lake Blvd grade separations (RR and TH10) substantially complete
    • Bridges will be painted soon, including City logo
    • Trail paving will be completed soon
    • Additional signing will be installed soon
  • Ramsey Blvd grade separations (RR and TH10) construction in progress
    • Substantial completion anticipated by end of September
  • Final completion anticipated June 2026
  • Project webpage https://www.anokacountymn.gov/3918/Hwy-10Ramsey-Blvd-Interchange
 
City of Anoka Improvement Projects
Ferry Street (Trunk Highway 47) Grade Separation of BNSF Rail Crossing
  • City-led project
  • $45M in bonds authorized October 2020
  • 2028 construction anticipated
Highway 47 Corridor Improvements – Garfield St to Bunker Lk Blvd
  • Combined with above City-led project
  • 3-lane design
  • Received regional solicitation funds for 2027 construction
  • Permanent signal system at McKinley Street
  • Construction proposed for 2027 - 2029
 
Anoka County Improvement Projects
  • No updates.
 
MnDOT Improvement Projects
Highway 10 Mill & Overlay and RCI Improvements
  • Mill & Overlay US 10/169 pavement from approx. ½-mile west of Cleveland/Jarvis Avenue in Elk River to ½-mile west of Ramsey Boulevard in Ramsey, including Dayton Rest Area
  • Construct Reduced Conflict Intersection (RCI) improvements for the intersections of Edison Street and Jarvis Street in Elk River, and Alpine Drive and Beatty Drive in Ramsey
    • Construct J-Turns
    • Remove median crossings
  • Extend pedestrian trail south of US 10/169 from 500-feet East of Adams Street to Edison Street
  • Construct pedestrian refuge in median of US 10/169 at Jarvis Street
  • Repair/replace culverts
  • Construct/repair/replace misc. guardrail treatments
  • 2027 construction proposed
 
Studies & Items of Interest
Wetland 114 P staff updates
  • Staff continues to monitor water levels.
  • Will provide updates as applicable.
Commercial/Industrial/Residential Developments
  • Staff can respond to questions as needed. 
Staff will present an update on the Waterfront splash pad project
 
PWC Future Topics Calendar Discussion Items
See calendar in the next case. 
 

Notification:

Notification is not required for this case. 

Time Frame/Observations/Alternatives:

Staff estimates up to 60 minutes will be needed for updates and discussion. 

Recommendation:

Staff can offer recommendations on specific items upon request. 

Outcome/Action:

No formal action required.  For Committee review and discussion purposes only. 

Attachments

No file(s) attached.

Form Review

Inbox Reviewed By Date
Brian Hagen Brian Hagen 07/11/2025 01:20 PM
Form Started By:
Bruce Westby
Started On:
07/11/2025 11:52 AM
Final Approval Date:
07/11/2025