5.2.
| CC Regular Session |
| Meeting Date: | 10/28/2025 |
| Primary Strategic Plan Initiative: | {ud_pd8} |
Title:
Approve partial payment #28 to Magney Construction, Inc. for improvement project #21-09; Centralized Water Treatment Plant.
Purpose/Background:
Pay Estimate and Resolution attached.
Recommendation:
The Resident Project Representative from Advanced Engineering and Environmental Services (AE2S) has inspected the completed work and recommends partial payment #28 to Magney Construction, Inc. for said project in the amount of $1,222,538.50.
Outcome/Action:
Adopt Resolution #25-252 approving partial payment #28 to Magney Construction, Inc., of Chanhassen, Minnesota; for Improvement Project #21-09; Centralized Water Treatment Plant, in the amount of ?$1,222,538.50.
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Bruce Westby | Bruce Westby | 10/23/2025 07:33 AM |
| Bruce Westby | Bruce Westby | 10/23/2025 10:19 AM |
| Brian Hagen | Brian Hagen | 10/23/2025 10:29 AM |
- Form Started By:
- Marsha Weidner
- Started On:
- 10/17/2025 09:18 AM
- Final Approval Date:
- 10/23/2025