Title:
Adopt Resolution #25-273 Authorizing Final Payment to Dave Perkins Contracting, Inc., for Improvement Project #25-61, Waterfront - Water-Play Utility Improvements.
Purpose/Background:
Resolution and Pay Request Attached.
Time Frame/Observations/Alternatives:
Issuing final payment will be contingent on receipts of the following items from Dave Perkins Contracting, Inc.
- IC 134 (Contractor's Withholding Affidavit showing compliance with the provisions of Minnesota Statute 290.92 requiring withholding state income tax).
- Waiver of Mechanic's Lien Rights (Affidavit that all claims against Dave Perkins Contracting, Inc. by reasons of contract have been fully paid or satisfactorily secured).
- Consent of Surety to Final payment (Certification from the contractor's surety).
Recommendation:
The Senior Engineering Technician has inspected the completed work and recommends final payment to Dave Perkins Contracting, Inc. of Nowthen, Minnesota in the amount of $131,556.00.
Outcome/Action:
Motion to adopt Resolution #25-273 Authorizing Final Payment to Dave Perkins Contracting, Inc. for Improvement Project #25-61, Waterfront - Water-Play Utility Improvement in the amount of $131,556.00.
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Bruce Westby | Bruce Westby | 11/20/2025 01:01 PM |
| Brian Hagen | Brian Hagen | 11/20/2025 03:37 PM |
- Form Started By:
- Marsha Weidner
- Started On:
- 11/13/2025 10:47 AM
- Final Approval Date:
- 11/20/2025