City Improvement Projects
#26-01 MSA Bunker Lake Boulevard Reconstruction
  • Bolton & Menk, Inc. is preparing final plans and specifications
  • 2026 construction proposed
  • See separate case
#26-02 2026 MSA Pavement Overlay Improvements
  • Preparing plans and specifications in-house
  • 2026 construction proposed
#26-03 Carol-Rose Acres & Sports Haven Reconstructions
  • Preparing plans and specifications in-house
  • 2026 construction proposed
#26-04 Countryside Estates Reconstructions
  • Preparing plans and specifications in-house
  • 2026 construction proposed
  • See separate case
#26-05 Flintwood Hills 2nd & 3rd Reconstructions
  • Preparing plans and specifications in-house
  • 2026 construction proposed
#26-06 Riverside West Reconstructions
  • Preparing plans and specifications in-house
  • 2026 construction proposed
#26-07 Section 01 Unplatted (S. CR 27) Reconstructions
  • Preparing plans and specifications in-house
  • 2026 construction proposed
  • See separate case
#26-08 2026 Neighborhood Pavement Overlay Improvements
  • Preparing plans and specifications in-house
  • 2026 construction proposed
  • See separate case
#25-03 MSA Alpine Drive Reconstruction – CSAH 57 to TH 47
  • Construction complete
  • Punch list items are being addressed
#25-04 Dickenson’s Mississippi Estate Street Reconstruction
  • Construction complete
  • Punch list items are being addressed
#25-05 High Point Street Reconstruction
  • Construction complete
  • Punch list items are being addressed
#25-06 Sortebergs Street Reconstruction
  • Construction complete
  • Punch list items are being addressed
#25-07 2025 Neighborhood Pavement Overlay Improvements
  • Construction complete
  • Punch list items are being addressed
#25-08 Sunwood Drive Crosswalk Repairs
  • Preparing plans and specifications in-house
  • 2026 construction proposed
#25-12 COR Street Lighting Improvements
  • Street lights proposed along Ramsey Parkway and at intersections
  • 2026 construction proposed
  • See separate case requesting a recommendation for City Council to authorize Connexus Energy to provide design services
#25-58 Waterfront Water Play Area Improvements
  • City utilities work complete (IP #25-51)
  • Mass grading work complete (IP #25-62)
  • Plan preparation almost complete
  • LRRWMO Permit application will be submitted soon for potential approval January 15, 2026
  • Construction proposed to begin February 2026
#24-03 2024 NE Ramsey Street Reconstruction
  • Construction complete
  • Closing project out
#24-13 Fox Ridge Estates 1st and 2nd Additions Street Reconstruction
  • Construction complete
  • Closing project out
#24-51 TH 47 Trail Gap Connection – 142nd Avenue to Xkimo Street
  • Bolton & Menk prepared draft construction plans and specifications for 10’ pedestrian trail
  • Plans need updating per final grading of Complete Auto and Lightbridge Academy developments
  • MnDOT proposes to construct this trail with their 2028 TH 47 mill and overlay project
#21-09 Centralized Water Treatment Plant
  • Construction in progress
  • City Council will tour in January when operational
#20-11 Ramsey Gateway Highway 10 Improvements
  • Project complete
  • Punch list items are being addressed
 
City of Anoka Improvement Projects
Ferry Street (Trunk Highway 47) Grade Separation of BNSF Rail Crossing
  • City-led project
  • $45M in bonds authorized October 2020
  • 2028 construction anticipated
Highway 47 Corridor Improvements – Garfield St to Bunker Lk Blvd
  • Combining with above City-led project
  • 3-lane design
  • Received regional solicitation funds for 2027 construction
  • Permanent signal system at McKinley Street
  • Construction proposed for 2027 - 2029
 
Anoka County Improvement Projects
  • NEW - Sunfish Lake Blvd. is proposed to be reconstructed north of Bunker Lake Blvd. in 2026.
 
MnDOT Improvement Projects
Highway 10 Mill & Overlay and RCI Improvements
  • 30-percent plans complete – Staff reviewed and submitted comments to MnDOT
  • Mill & Overlay US 10/169 pavement from approx. ½-mile west of Cleveland/Jarvis Avenue in Elk River to ½-mile west of Ramsey Boulevard in Ramsey, including Dayton Rest Area
  • Constructing Reduced Conflict Intersection (RCI) improvements at the intersections of Edison Street and Jarvis Street in Elk River, and Alpine Drive and Beatty Drive in Ramsey
    • Removing median crossovers and installing J-Turns w/out signal systems
  • Extending pedestrian trail south of US 10/169 from 500-feet East of Adams Street to Edison Street
  • Constructing pedestrian crossover/refuge in median of US 10/169 at Jarvis Street
  • Removing, repairing and replacing drainage culverts
  • Constructing, repairing and replacing misc. guardrail/end treatments
  • 2027 construction proposed
  • No public open houses are scheduled yet
 
Studies & Items of Interest
Wetland 114P Outlet Control Structure
  • Staff continue to monitor water levels.  No updates at this time.
Commercial/Industrial/Residential Developments
  • Staff can respond to questions as needed. 
 
Miscellaneous Staff Updates
  • Parking restriction signs have been installed in the Village of Sunfish Lake
 
PWC Future Topics Calendar Discussion Items
  • See calendar in following case. 

Notification:

Not required for this case.

Time Frame/Observations/Alternatives:

Staff estimates up to 15 minutes will be needed for updates and discussion. 

Recommendation:

Staff can offer recommendations on specific items upon request. 

Outcome/Action:

No formal action required.  For Committee review and discussion purposes only.  

Attachments

No file(s) attached.

Form Review

Inbox Reviewed By Date
Brian Hagen Brian Hagen 12/11/2025 01:31 PM
Form Started By:
Bruce Westby
Started On:
11/25/2025 05:39 PM
Final Approval Date:
12/11/2025