5.9.
CC Regular Session
Meeting Date: 09/08/2026
   
Primary Strategic Plan Initiative: Address infrastructure needs.

Title:

Adopt Resolution #26-201 Awarding Construction Staking Contract for 2026 MSA Overlay Improvements, Improvement Project #26-02

Purpose/Background:

Purpose:
The purpose of this case is to adopt Resolution #26-201 awarding a construction staking contract for 2026 MSA Overlay Improvements, Improvement Project #26-02 to Hakanson Anderson Associates for the not-to-exceed amount of $8,300.00

Background:
On August 25, 2026, City Council adopted Resolution #26-195, awarding a construction contract to North Valley, Inc. for 2026 MSA Overlay Improvements, Improvement Project #26-02.

Construction staking is essential to the construction of said improvements, and city staff does not have the capacity to perform construction staking in-house.

Hakanson Anderson Associates submitted a proposal for construction staking of the proposed improvements for a total amount of $8,300.00.

City staff proposes to administer and inspect construction. Plans and specifications were prepared in-house as part of staff’s normal duties.

Notification:

Notifications are not required as part of this case.

Time Frame/Observations/Alternatives:

Alternatives:
Motion to adopt Resolution #26-201 awarding a construction staking contract for 2026 MSA Overlay Improvements, Improvement Project #26-02 to Hakanson Anderson Associates for the not-to-exceed amount of $8,300.00

Funding Source:

On August 25, 2026, City Council adopted Resolution #26-195 awarding a construction contract to North Valley, Inc. for said overlay improvements in the total bid amount of $1,129,093.12. Adding indirect costs in the amount of 14-percent, the total project costs are estimated to be $1,287,166.16. Hakanson Anderson Associates has provided a construction staking proposal for a not-to-exceed amount of $8,300.00. Construction staking is included in the 14-percent indirect project costs. These costs are proposed to be funded using a combination of Municipal State Aid and Storm Water Utility Funds.

Recommendation:

Staff recommends adopting Resolution #26-201 awarding a construction staking contract for 2026 MSA Overlay Improvements, Improvement Project #26-02 to Hakanson Anderson Associates for the not-to-exceed amount of $8,300.00.

Outcome/Action:

Motion to adopt Resolution #26-201 awarding a construction staking contract for 2026 MSA Overlay Improvements, Improvement Project #26-02 to Hakanson Anderson Associates for the not-to-exceed amount of $8,300.00.

Attachments

Form Review

Inbox Reviewed By Date
Brian Hagen Brian Hagen 09/03/2026 12:57 PM
Form Started By:
Joe Feriancek
Started On:
08/26/2026 07:47 AM
Final Approval Date:
09/03/2026