5.2.
HRA Regular Session
- Meeting Date:
- 06/12/2012
- Submitted For:
- Kurt Ulrich
- By:
- Bill Goodrich, Administrative Services
Title:
Update on Sunwood Drive Realignment Project - PORTIONS OF THIS DISCUSSION MAY BE CLOSED TO THE PUBLIC
Background:
The Council discussed this case earlier this evening with portions of the discussion closed to the public. This item is now on the HRA agenda to update the HRA and to discuss the HRA responsibilities relative to the Sunwood Drive reralignment project.
Observations:
A breakdown of all costs attributable to the Sunwood Realignment Project are as follows:
The funding package for this project, as previously approved by the City Council is as follows:
A revised accounting, based upon the most current estimates, is as follows:
As can be seen above there is approximately $289,000 that is unaccounted for with this project. This overage is primarily the costs for streetlighting and construction administration/testing. Staff intends to make adjustments for a portion of the soft costs (engineering/testing) such that the appropriate enterprise funds pay their pro-rata share. City staff was preparing to perform the construction administration on this project, but due to recent staffing changes we will have to review this matter to determine what can be accomplished in house, and what will have to be contracted. It is proposed that the Streetlight Utility will fund the streetlighting component of this project.
The Housing and Redevelopment Authority (HRA) will have to discuss the COR land sale proceeds referenced above to determine whether they are interested in deviating from their land sale distribution policy, and apply the entire amount of a pending land sale to this improvement project. A final funding package will be brought forward, clarifying these matters, after the bids are opened and a project is proposed to be awarded (June 26, 2012).
| Land Acquisition | $2,700,000 |
| Armstrong Blvd | $1,650,000 |
| Sunwood Drive | $1,075,000 |
| COR Grading & Northstar Market Place Access Revisions | $210,000 |
| Streetlighting | $112,000 |
| Engineering/Construction Administration/Testing | $470,000 |
| TOTAL | $6,217,000 |
The funding package for this project, as previously approved by the City Council is as follows:
| Anoka County | $1,700,000 |
| LRIP Grant | $500,000 |
| Equipment Revolving Fund | $1,056,450 |
| TIF #2 | $500,000 |
| Stormwater Utility Fund | $255,484 |
| Water Utility Fund | $238,066 |
| EDA (Nordvik acquisition) | $600,000 |
| Excess Rail Funding | $500,000 |
| TOTAL | $5,350,000 |
A revised accounting, based upon the most current estimates, is as follows:
| Anoka County | $1,700,000 |
| LRIP Grant | $500,000 |
| Equipment Revolving Fund | $1,056,450 |
| TIF #2 | $500,000 |
| Stormwater Utility Fund | $230,500 |
| Water Utility Fund | $210,000 |
| Sanitary Sewer Utility Fund | $19,000 |
| EDA (Nordvik acquisition) | $600,000 |
| Excess Rail Funding | $500,000 |
| Streetlight Utility | $112,000 |
| COR land sale proceeds * | $500,000 |
| TOTAL | $5,927,950 |
As can be seen above there is approximately $289,000 that is unaccounted for with this project. This overage is primarily the costs for streetlighting and construction administration/testing. Staff intends to make adjustments for a portion of the soft costs (engineering/testing) such that the appropriate enterprise funds pay their pro-rata share. City staff was preparing to perform the construction administration on this project, but due to recent staffing changes we will have to review this matter to determine what can be accomplished in house, and what will have to be contracted. It is proposed that the Streetlight Utility will fund the streetlighting component of this project.
The Housing and Redevelopment Authority (HRA) will have to discuss the COR land sale proceeds referenced above to determine whether they are interested in deviating from their land sale distribution policy, and apply the entire amount of a pending land sale to this improvement project. A final funding package will be brought forward, clarifying these matters, after the bids are opened and a project is proposed to be awarded (June 26, 2012).
Funding Source:
The funding for this project has been identified above.
Council Action:
This case is for information - no action is required at this time. The HRA may direct staff to prepare a resolution for future action that would allow a deviation from the policy for distribution of land sale proceeds to allow funds to be designated toward this project.