4.7.
CC Regular Session
- Meeting Date:
- 07/24/2012
- Submitted For:
- Len Linton
- By:
- Len Linton, Engineering/Public Works
Information
Title:
Consider Change Order for City Improvement Project #12-24 Division B
Background:
Last summer the City experienced several significant rainfall events that let to many localized flooding concerns and resident complaints. The large volumes of precipitation that occurred over a short period of time appears to have elevated the groundwater within areas of the City and prohibited the generous rate of infiltration that typically takes place in the the Anoka sandplain. The concerns were discussed several times at the Public Works Committee and three categories were established:
- Those that required no further action.
- Those that required additional investigation and evaluation before deciding on a long term solution and implementing corrective actions.
- Those that had an identified recommendation for immediate action.
Recommendation:
Staff recommends approving this change order for tree removal and grading in the amount of $8,660.
Funding Source:
Funding for this project is from the Storm Water Utility account.
Council Action:
Motion to authorize the proposed change order for tree removal and grading in the amount of $8,660.
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Kurt Ulrich | Kurt Ulrich | 07/18/2012 11:31 PM |
- Form Started By:
- Len Linton
- Started On:
- 07/18/2012 09:26 AM
- Final Approval Date:
- 07/18/2012