Consider Request for Reimbursement of Utility Repair Costs - PSD, LLC
Background:
PSD, LLC has submitted a request to the City Council to be reimbursed for some costs incurred during the construction of the Ramsey Office Plaza.
Attached is a memo outlining their claim that there were errors in the installation of utilities in Sunwood and Sapphire. As a result, PSD had additional costs associated with the construction of their utility connections.
Attached is a memo outlining their claim that there were errors in the installation of utilities in Sunwood and Sapphire. As a result, PSD had additional costs associated with the construction of their utility connections.
Notification:
Observations:
Recommendation:
Staff recommends the City Council consider their request and provide feedback on a policy level basis as to how these requests should be handled. There are a number of situations throughout The COR where existing property owners have additional costs related to the state of improvements as left by the developer at that time.
Funding Source:
N/A
Council Action:
Provide consensus direction on a policy level so staff can prepare and process PSD's request accordingly.
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Kurt Ulrich | Kurt Ulrich | 07/26/2012 12:45 PM |
- Form Started By:
- dlazan
- Started On:
- 07/26/2012 12:17 PM
- Final Approval Date:
- 07/26/2012