Skip to main content

AgendaQuick™

View Agenda Item

5.2.
HRA Regular Session
Meeting Date:
08/13/2012
By:
Darren Lazan, Housing & Redevelopment Authority

Information

Title:

Consider Award of Construction Project - North Commons

Background:

At the regular meeting of the HRA on July 10, 2012, the HRA approved plans and specifications for North Commons, the 17 lot subdivision on HRA property.  This work consists of the grading, utilities, street, and storm sewer improvements necessary to develop the proposed property.

When plans and specifications were ordered, the project scope was used to develop a pro-forma which was presented to the HRA for approval. This pro-forma contemplates the cost of development, city development fees, and proceeds remaining for the HRA. This pro-forma was approved by the HRA and contemplated a break-even proposition for the HRA at an average lot price of $35,000. This presumes all development costs and development fees were paid to the city, and the HRA received their land costs back from the sale of these lots.

The first of these lots is under contract for sale at $35,000.

Bids were received and opened Tuesday August 7th, 2012.  Three contractors bid the project.  One contractor bid all 8 sections of the proposed work, while two other contractors combined to cover all 8 sections.  The apparent low bid was in the amount of $461,752.00 and was proposed by Dave Perkins and Sauter and Sons.  The pro-forma estimate for construction costs was roughly $330,000.  The $160,000 difference can be accounted for in a couple significant components. 

During the review of the plans by LRRWMO, they requested our project meet the new requirements of the Generation 3 plan which would have added considerable cost to the project.  While we were able to negotiate a reasonable solution, there were still items added to the plans that were not contemplated in the original approvals for this area, or in the original pro-forma.
  • The addition of an outlet pipe from the existing North Commons pond.
  • Additional fill to create a greater separation from the high water elevation.
  • Modifications to the existing storm water system.
There were additional costs for grading and import of material due to proximity to the site.  The original pro-forma contemplated material available for this project from the area now excavated as Lake Ramsey.  When the HRA agreed to allow that material to be used for fill on BOTH Armstrong Boulevard and Sunwood Drive we depleted the available material.  We will now open a second borrow area east of the tree line and west of proposed Center Street.  There were higher grading costs associated with that effort.

Finally, the project is carrying both the initial contribution for the park construction, as well as the additional costs associated with the soil corrections approved by the HRA.  This is currently approximately $40,000.


Observations:

The development team modified the pro-forma with the revised construction numbers to evaluate the impact on the proceeds. Assuming ALL of the additional costs are carried by this development, which is arguable as to appropriate allocation.

The result of the additional construction cost drives the break-even price per lot to approximately $42,000.  While this is above the current offer, we believe the market will rise as these lots are developed, and accordingly so will the average price realized.

The development team believes the project remains a positive improvement to The COR for the following reasons:
  • The project will bring in approximately $200,000 in development fees that would otherwise not be realized - including $42,000 in park dedication fees needed to develop North Commons Park.
  • The project will bring additional tax base to the community.
  • The project will contribute funds to the cost of a second lift on existing streets
  • Progress and improvements in the North Commons area will improve salability and home values.
  • The project will make certain infrastructure improvements necessary, but without funding solutions currently.


Notably, North Pines Aggregate, apparent high bidder, has stated some concerns regarding the process.  .  .  The City Attorney is reviewing the bid process and will report at the meeting in regard to whether the apparent low bid is legally acceptable. 

 



Recommendation:

Subject to approval by the Attorney, the development team records the HRA approve the bid received from Dave Perkins Contracting and Sauter and Sons Excavating for the combined amount of $461,762.00.

The development team recommends the HRA approve the revised pro-forma attached and proceed with the development of North Commons as planned.

Funding Source:

Landfill Trust Fund - as loan on sale proceeds - $400,000
Stormwater Management Fund - for area storm water improvements - $50,000

Staff is also reviewing whether County HRA funds are eligible to use on this project.

Council Action:

Award contract for the construction of North Commons to Dave Perkins Construction and Sauter and Sons as outlined on the project bid tabulation.

Approve the revised project pro-forma and direct the development team to proceed with the project based on costs outlined within the pro-forma.

Attachments

Form Review

Inbox Reviewed By Date
Kurt Ulrich Kurt Ulrich 08/09/2012 03:27 PM
Form Started By:
dlazan
Started On:
08/08/2012 01:29 PM
Final Approval Date:
08/09/2012