4.8.
CC Regular Session
Meeting Date:
08/11/2015
Submitted For:
Len Linton
By:
Len Linton, Engineering/Public Works

Information

Title

Adopt Resolution #15-08-198 Authorizing Acquisition of a Permanent Easement Necessary for the Construction of a Storm Sewer Line

Purpose/Background:

The City identified the need for a storm sewer line to serve the 144th Avenue extension project.  The end of the line terminates on property owned by the Minnesota Pollution Control Agency (MPCA).  The City negotiated for and received assurances that the MPCA would grant the required easement.  The City prepared plans, received bids and constructed the project. 
 
The MPCA conducted a review of their easements in this area in 2014 and determined that this storm sewer easement had not been recorded at Anoka County.

The attached Resolution #15-08-198 authorizes acquisition of the easement over the storm sewer line that terminates on the MPCA property. 

Notification:

Notification of adjacent land owners is not required.

Observations/Alternatives:

The storm sewer line was installed in 2008 based on the agreement with the MPCA to obtain the necessary easement.

Funding Source:

The MPCA has not requested reimbursement for the acquisition of the utility easement.

Recommendation:

Staff recommends approving Resolution #15-08-198 Authorizing Acquisition of a Permanent Easement Necessary for the Construction of a Storm Sewer Line.

Action:

Motion to adopt Resolution #15-08-198 Authorizing Acquisition of a Permanent Easement Necessary for the Construction of a Storm Sewer Line.

Attachments

Form Review

Inbox Reviewed By Date
Diana Lund Diana Lund 08/05/2015 11:54 AM
Kurt Ulrich Jo Thieling 08/05/2015 03:48 PM
Form Started By:
Len Linton
Started On:
08/05/2015 10:59 AM
Final Approval Date:
08/05/2015