4.13.
CC Regular Session
- Meeting Date:
- 08/25/2015
- Submitted For:
- Patrick Brama
- By:
- Kathy Schmitz, Administrative Services
Information
Title
Adopt Resolution #15-08-207 Approving Partial Payment to Construction Results Corporation for IP #14-28 Parking Ramp Garage Enclosure
Purpose/Background:
Resolution and Pay Request attached.
Recommendation:
SRF Consulting, the project manager hired by the City, has inspected the completed work and recommends partial payment to Construction Results Corporation for IP #14-28, parking ramp enclosure, in the amount of $63,260.50.
Action:
Motion to Adopt Resolution #15-08-207 Approving Partial Payment to Construction Results Corporation for IP #14-28 Parking Ramp Garage Enclosure.
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Kurt Ulrich | Kurt Ulrich | 07/22/2015 02:27 PM |
| Kurt Ulrich | Kurt Ulrich | 08/20/2015 03:09 PM |
- Form Started By:
- Kathy Schmitz
- Started On:
- 07/14/2015 11:56 AM
- Final Approval Date:
- 08/20/2015