6.3.
Public Works Committee
- Meeting Date:
- 07/19/2016
- By:
- Bruce Westby, Engineering/Public Works
Title:
Staff Updates on Improvement Projects and Items of Interest
Purpose/Background:
The purpose of this case is to update the Public Works Committee on active and proposed improvement projects within the City, and on other items of interest to the Committee as noted below.
MnDOT Improvement Projects
MnDOT Improvement Projects
- TH 47 at 142nd Avenue
- Remove left turns from southbound TH 47 to eastbound 142nd Avenue
- Construction proposed currently scheduled from August 22, 2016 to Sept. 25, 2016
- Project web site link: http://www.dot.state.mn.us/metro/projects/hwy47/index.html
- CR 116/Bunker Lake Boulevard Pavement Reclamation and Overlay – Ramsey Boulevard to Basalt Street
- Existing pavement was reclaimed and overlaid with 4” new pavement
- Construction complete (except left/right turn arrows)
- CR 83/Armstrong Boulevard Pavement Reclamation and Overlay – 149th Lane to 173rd Avenue
- Existing pavement to be reclaimed and overlaid with 4” new pavement
- Bypass lanes added at 154th, 157th, and 163rd Avenues
- Right turn lanes added at 155th and Tiger Avenues
- New striping and signs
- Construction scheduled from September 12th through October 14th (will not interfere with Game Fair)
- Business Park 95 Regional Stormwater Pond Improvements
- June 28th – Council accepted bids and awarded Construction Contract to New Look Contracting, Inc.
- Currently executing Construction Contract
- Construction to occur in July / August 2016 (dry season)
- Andrie Street & 164th Lane Reconstruction
- May 24th – Council awarded Construction Contract to Douglas-Kerr Underground, LLC
- June 23rd – Construction began (3 phases)
- Phase 1 - South end of Andrie Street between Alpine Drive and Muirfield Court (1 month)
- Phase 2 - North end of Andrie Street between Muirfield Court and 164th Lane (1 month)
- Phase 3 - 164th Lane (1 month)
- Project completion scheduled for early October 2016
- 2016 Sealcoat Project
- June 28th – Council accepted bids and awarded Construction Contract to Pearson Bros, Inc.
- Currently executing Construction Contract
- Construction to occur July to mid-August 2016
- 2016 Overlay Project
- June 14th – Council approved plans & authorized bids
- July 14th – Bids to be opened
- July 26th – Council to consider accepting bids & awarding a construction contract
- Construction proposed to begin early August
- Project completion proposed by September 16th
- Riverdale Drive Extension - Traprock St. to Ramsey Blvd.
- Plans and specifications 95% complete
- Parks property appraisal complete
- Scheduling Anoka County Parks meeting to discuss mutually beneficial acquisition of 5.3 acres R/W
- TH 47 Crosswalk Improvements @ Nowthen Blvd / Xkimo Street **COMPLETE**
- 2017 COR Concrete Pavement Improvements
- Numerous concrete pavement sections require repairs, especially crosswalks
- Temporary pavement repairs proposed for 2016 (est. $20,000)
- Permanent repairs proposed for 2017 ($150,000 in CIP)
- Staff is researching improvement options, then will design improvements and prepare plans
- Options tentatively proposed to be presented to Public Works Committee this October
- Sunwood Drive Striping Improvements
- Temporary striping improvements proposed for 2016 (est. $5,000)
- Coordinate / incorporate permanent striping improvements with concrete pavement improvements
- August Public Works Committee meeting – Cancel August meeting or schedule alternate date to August 16th?
Timeframe:
Staff estimates less than 10 minutes will be needed for updates and discussion.
Observations/Alternatives:
N/A
Funding Source:
N/A
Recommendation:
N/A
Action:
No action required.
Attachments
No file(s) attached.
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Grant Riemer | Grant Riemer | 07/13/2016 10:38 AM |
| Kurt Ulrich | Kathy Schmitz | 07/14/2016 01:46 PM |
- Form Started By:
- Bruce Westby
- Started On:
- 07/12/2016 06:58 AM
- Final Approval Date:
- 07/14/2016