6.2.
Public Works Committee
- Meeting Date:
- 11/15/2016
- By:
- Bruce Westby, Engineering/Public Works
Title:
Staff Updates on Improvement Projects and Items of Interest
Purpose/Background:
The purpose of this case is to update the Public Works Committee on current and proposed improvement projects within the City, and on other items of interest to the Committee.
City Improvement Projects
?
City Improvement Projects
- Business Park 95 Regional Stormwater Pond Improvements
- Work is substantially complete
- Final payment will occur in 2017 following satisfactory completion of punch list and warranty work
- Andrie Street & 164th Lane Reconstruction
- Work is substantially complete
- Final payment will occur in 2017 following satisfactory completion of punch list and warranty work
- Riverdale Drive Extension - Traprock St. to Ramsey Blvd.
- Plans and specifications 95% complete
- In process of acquiring 5.3 acres of roadway right-of-way from Anoka County Parks (appraised value $200,000)
- Construction to occur in 2017
- Mississippi River Trail Phase 3
- Final grading nearing completion
- Aggregate base and paving may be completed in 2016, weather depending
- Final completion scheduled for 2017
- Jarvis Street Railroad Crossing Quiet Zone Improvements
- This rail crossing was established as a quiet zone on October 31, 2016
- Zeolite Street Storm Sewer Extension Improvements
- Work is substantially complete
- Final payment will occur in 2017 following satisfactory completion of punch list and warranty work
?
Timeframe:
Staff estimates less than 10 minutes will be needed for updates and discussion.
Observations/Alternatives:
N/A
Funding Source:
N/A
Recommendation:
N/A
Action:
N/A
Attachments
No file(s) attached.
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Grant Riemer | Grant Riemer | 11/09/2016 03:33 PM |
| Kurt Ulrich | Kurt Ulrich | 11/10/2016 01:39 PM |
- Form Started By:
- Bruce Westby
- Started On:
- 11/09/2016 01:25 PM
- Final Approval Date:
- 11/10/2016