Skip to main content

AgendaQuick™

View Agenda Item

6.3.
Public Works Committee
Meeting Date:
05/16/2017
By:
Bruce Westby, Engineering/Public Works

Title:

Staff Updates on Improvement Projects and Items of Interest

Purpose/Background:

The purpose of this case is to update the Public Works Committee on current and proposed improvement projects within the City, and on other items of interest to the Committee.

City Improvement Projects
  • Business Park 95 Regional Stormwater Pond Improvements
    • Work is substantially complete
    • Final payment will occur in 2017 following satisfactory completion of punch list and warranty work
  • Andrie Street & 164th Lane Reconstruction
    • Work is substantially complete
    • Final payment will occur in 2017 following satisfactory completion of punch list and warranty work
  • Mississippi River Trail Phase 3
    • Work is substantially complete
    • Final completion scheduled for summer 2017
  • Zeolite Street Storm Sewer Extension Improvements
    • Work is substantially complete
    • Final payment will occur in 2017 following satisfactory completion of punch list and warranty work
  • Riverdale Drive Extension - Traprock St. to Ramsey Blvd.
    • Plans and specifications are complete
    • Working with Anoka County Parks to acquire 5.3 acres of roadway right-of-way (appraised value $200,000)
    • Construction proposed for 2017 (pending right of way acquisition)
  • Alpine Drive Reconstruction
    • Out for bids
    • Construction proposed from June 26th through September 22nd (open to traffic August 26th)
  • Sunwood Drive Reconstruction
    • Out for bids
    • Construction proposed from June 26th through September 29th
 
Anoka County Improvement Projects
  • Hanson Boulevard/CSAH 78 Grade Separation @ BNSF Railway Crossing (2017)
    • Reconstruct County State Aid Highway 78 (CSAH 78) / Hanson Boulevard to a 4-lane divided section
    • Construct a grade-separated overpass for Burlington Northern Sante Fe (BNSF) railway crossing
  • Hanson Boulevard/CSAH 78 Reconstruction (2018)
    • Expand CSAH 78 / Hanson Blvd between 139th Ave and CSAH 18 / Crosstown Blvd to 4-lane divided section
  • Foley Boulevard/CSAH 11 Grade Separation @ BNSF Railway Crossing
    • This project is currently unscheduled and unfunded
 
MnDOT Improvement Projects
  • Trunk Highway 10 Cable Median Barrier Installation (2018)  
    • Install cable median barrier along Highway 10 between Thurston Avenue and Highway 101 
  • Ferry Street / Trunk Highway 47 Grade Separation @ BNSF Railway Crossing (2017)
    • Preliminary design underway
 
Items of Interest
  • Puma St & Bunker Lake Blvd Improvements
  • Updating Wellhead Protection Plan
  • Request for Quotes for Ground Penetrating Radar, Pavement Corings and Soil Borings on Street Maintenance Projects in 2018 & 2019 CIP


 

Timeframe:

Staff estimates that 10 minutes will be needed for updates and discussion.

Observations/Alternatives:

N/A

Funding Source:

N/A

Recommendation:

N/A

Action:

N/A

Attachments

No file(s) attached.

Form Review

Inbox Reviewed By Date
Grant Riemer MaryJo Warner 05/11/2017 10:53 AM
Kurt Ulrich MaryJo Warner 05/11/2017 04:08 PM
Form Started By:
Bruce Westby
Started On:
05/10/2017 03:03 PM
Final Approval Date:
05/11/2017