Staff Updates on Improvement Projects and Items of Interest

Purpose/Background:

Purpose/Background:
The purpose of this case is to update the Public Works Committee on current and proposed improvement projects within the City, and on other items of interest to the Committee.

City Improvement Projects
  • Riverdale Drive Extension - Traprock St. to Ramsey Blvd. (#16-20)
    • Construction complete
    • Only punch list items remain
    • Final payment in 2019
  • River’s Bend Street Reconstructions (#17-02)
    • Construction complete
    • Only punch list items remain
    • Final payment in 2019
  • Puma Street Utilities Extensions (#17-10)
    • Construction complete
    • Only punch list items remain
    • Final payment in 2019
  • Stanhope Terrace Street Reconstructions (#18-00)
    • Construction complete
    • Only punch list items remain
    • Final payment in 2019
  • 2018 Street Overlay Improvements (#18-03)
    • Construction substantially complete
    • Final payment 2019
  • 2018 Crackseal and Sealcoat Improvements (#18-04)
    • Cracksealing nearly complete
    • Sealcoating scheduled for week of July 16
  • The COR Regional Infiltration Basin (#18-09)
    • Plans & Specifications nearly complete
    • Excess fill to be placed throughout The COR
    • Anticipate City Council approval to authorize bids August 6th
    • Construction proposed to start this fall
    • Final completion proposed in 2019
  • Bunker Lake Boulevard and Puma Street Improvements (#18-05)
    • Construction anticipated to begin late August
    • Substantial completion anticipated mid-October
    • Final completion 2019
 
Anoka County Improvement Projects
  • Foley Boulevard/CSAH 11 Grade Separation @ BNSF Railway Crossing
    • Project is currently unfunded
 
MnDOT Improvement Projects
  • Ferry Street / Trunk Highway 47 Grade Separation @ BNSF Railway Crossing (2017)
    • Preliminary design on hold
    • Exploring realignment of Highway 47 to remove S-curve at fair grounds
    • Ramsey Staff will continue tracking this project
    • Combine with other Highway 10 improvement projects?
 
Items of Interest
  • Ground Penetrating Radar versus Pavement Cores
    • Staff requests Committee input on using GPR vs. pavement cores to verify constructed pavement sections

Timeframe:

Staff estimates 5 minutes will be needed for updates and discussion.

Observations/Alternatives:

N/A

Funding Source:

N/A

Recommendation:

N/A

Action:

No formal action required.  For Committee review and discussion purposes only.

Attachments

No file(s) attached.

Form Review

Inbox Reviewed By Date
Grant Riemer MaryJo Warner 07/12/2018 03:42 PM
Kurt Ulrich Kurt Ulrich 07/12/2018 04:07 PM
Form Started By:
Bruce Westby
Started On:
07/05/2018 02:55 PM
Final Approval Date:
07/12/2018