Title:
Acknowledge Preliminary Cost Estimates for Municipal Plaza and The Waterfront
Purpose/Background:
The purpose of this case is to acknowledge the preliminary cost estimates for Municipal Plaza and The Waterfront. At the July regular Park and Recreation Commission meeting, the Commission approved the refined concept plans for the two parks.
These cost estimates will be used to update Capital Improvement Plan, and evaluate the feasiblility of phased development of the parks as well.
These cost estimates will be used to update Capital Improvement Plan, and evaluate the feasiblility of phased development of the parks as well.
Notification:
Observations/Alternatives:
In 2014 the earlier concept plans were developed with rough cost estimates based upon square footage of the two parks' anticipated development intensity. In the last 4+ years (and with a booming construction economy), a 20% increase in the earlier constructed cost estimates would seem reasonable to account for inflation—and these estimates do match up, and are shown below:
Municipal Plaza, 2014 est. $3,510,000 20% inflationary est. $4,212,000
Municipal Plaza 2018 est. $4,125,600
The Waterfront, 2014 est. $6,224,040 20% inflationary est. $7,468,848
The Waterfront 2018 est $8,676,700
It may be important to note that these preliminary numbers include design fees, testing and an approxmate 8% contingency—additionally, the consistancy supports that these are realistic, likely costs of construction.
Municipal Plaza, 2014 est. $3,510,000 20% inflationary est. $4,212,000
Municipal Plaza 2018 est. $4,125,600
The Waterfront, 2014 est. $6,224,040 20% inflationary est. $7,468,848
The Waterfront 2018 est $8,676,700
It may be important to note that these preliminary numbers include design fees, testing and an approxmate 8% contingency—additionally, the consistancy supports that these are realistic, likely costs of construction.
Funding Source:
No funding is authorized or recommended as part of this case.
Recommendation:
Action:
No Action required—informational only.
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Grant Riemer | Grant Riemer | 08/02/2018 03:30 PM |
- Form Started By:
- Mark Riverblood
- Started On:
- 08/02/2018 11:20 AM
- Final Approval Date:
- 08/02/2018