Skip to main content

AgendaQuick™

View Agenda Item

4.10.
CC Regular Session
Meeting Date:
01/22/2019
Submitted For:
Bruce Westby
By:
Marsha Weidner, Engineering/Public Works

Information

Title

Adopt Resolution #19-030 Authorizing Final Payment to Park Contruction Company for Improvement Project 16-54; Mississippi River Trail - Phase III.

Purpose/Background:

Resolution and Pay Request Attached.

Observations/Alternatives:

Issuing final payment will be contingent on receipt of the following items from Park Contruction Company:
  1. IC 134 (Contractor’s Withholding Affidavit showing compliance with the provisions of Minnesota Statute 290.92 requiring withholding state income tax)
  2. Waiver of Mechanic’s Lien Rights (Affidavits that all claims against Park Contruction Company by reasons of the contract have been fully paid or satisfactorily secured)
  3. Consent of Surety to Final Payment (Certification from the contractor’s surety)
Following receipt of these items, final payment will be issued.

Recommendation:

Bolton & Menk, Inc. has inspected the completed work and recommends final payment to Park Construction Company for Improvement Project 16-54; Mississippi River Trial - Phase III in the amount of $12,366.79.

Final construction costs are $9,647.01 (1.5%) less than the awarded bid.

Action:

Motion to adopt Resolution #19-030 authorizing final payment to Park Construction Company for Improvement Project 16-54, Mississippi River Trail - Phase III in the amount of $12,366.79.

Attachments

Form Review

Inbox Reviewed By Date
Bruce Westby Bruce Westby 01/16/2019 03:33 PM
Kurt Ulrich Kurt Ulrich 01/17/2019 03:30 PM
Form Started By:
Marsha Weidner
Started On:
01/16/2019 09:57 AM
Final Approval Date:
01/17/2019