6.1.
Public Works Committee
- Meeting Date:
- 05/21/2019
- By:
- Bruce Westby, Engineering/Public Works
Title:
Staff Updates on Improvement Projects and Items of Interest
Purpose/Background:
The purpose of this case is to update the Public Works Committee on current and proposed improvement projects within the City, and on other items of interest to the Committee.
City Improvement Projects
Anoka County Improvement Projects
MnDOT Improvement Projects
Items of Interest
City Improvement Projects
- River’s Bend Street Reconstructions (#17-02)
- Complete punch list items and make final payment in 2019
- Stanhope Terrace Street Reconstructions (#18-00)
- Complete punch list items and make final payment in 2019
- 2018 Street Overlay Improvements (#18-03)
- Complete punch list items and make final payment in 2019
- Bunker Lake Boulevard and Puma Street Improvements (#18-05)
- Complete punch list items and make final payment in 2019
- The COR Regional Infiltration Basin (#18-09)
- Out for bids
- LRRWMO Permit requires completion by September 30, 2019
- Riverdale Drive Trunk Utility Improvements (#18-14)
- Utilities were operational April 30, 2019
- Final completion June 30, 2019
- 2019 Crackseal and Sealcoat Improvements (#19-00)
- Public Works Committee to discuss suspending sealcoat program 5/21
- Staff recommends continuing annual crack seal program
- Ford Brook Estates Street Reconstructions (#19-01)
- Executing contract
- Substantial completion in 2019
- Wood Pond Hills and Chestnut Ridge Street Reconstructions (#19-03)
- Executing contract
- Substantial completion in 2019
- RTC 9th Addition Pond Lining Improvements (#19-06)
- Engineering Staff provided plans to developer for quotes
- Engineer’s estimate = $50,000
- Developer to construct improvements with City reimbursement
- Wetland 114P Outlet Control Improvements (#19-07)
- Engineering Staff developing plans
- Final completion fall 2019
- Ferret Street and 147th Avenue Intersection Improvements (#19-08)
- Engineering Staff developing plans
- Public Works Staff completing work in 2019
- Germanium Street Drainage Improvements (#19-09)
- Engineering Staff developing plans
- Final completion summer 2019
- Hedgehog Street Drainage Improvements (#19-10)
- Engineering Staff developing plans
- Final completion summer 2019
- Misc. Drainage Improvements
- Other drainage improvements are under consideration
- Staff would prepare plans and specifications in-house
Anoka County Improvement Projects
- Roundabout at Armstrong Boulevard/CSAH 83 and Alpine Drive
- Anoka County received $1.35M in HSIP funds (est. project cost = $1.5M)
- Local cost share (Anoka County, City of Ramsey) = $150,000
- City of Ramsey costs set per Anoka County Cost Share Policy
- Anoka County to begin project design efforts in 2019/2020
- Construction planned for 2022/2023 pending City and County approvals
MnDOT Improvement Projects
- Ferry Street / Trunk Highway 47 Grade Separation @ BNSF Rail Crossing
- Preliminary design on hold
- MnDOT is exploring potential realignment of Highway 47 to remove S-curve at Anoka County fair grounds
- Staff communicated the comment made at the April 3rd Strategic Planning Meeting that Ramsey wants to be involved with traffic studies due to obvious impacts to the City of Ramsey
- MnDOT is considering combining this project with Anoka’s Highway 10 improvements, which are now fully funded
Items of Interest
- 17290 Germanium Street Drainage Concerns
- November 13, 2018 - Owner addressed City Council with drainage concerns
- December 18, 2018 - Owner presented concerns to Public Works Committee
- Late December 2018 - Staff collected topo on west property edge per Public Works Committee direction
- March 5, 2019 - Staff emailed updates to owner
- Late March 2019 - Owner submitted invoice to City for frozen septic system
- Early April 2019 - Staff collected topo on south property edge
- April 10, 2019 – Staff emailed updates to owner
- May 17, 2019 - Staff mailed letter to owner summarizing analysis/next steps
- Spring/summer 2019 - Covenant Meadows developer will install two 8-inch driveway culverts and regrade driveway with property owner input
- Northwest Metro Surface Water Supply Feasibility Study
- City participants include Corcoran, Dayton, Ramsey and Rogers
- Short Elliott Hendrickson (SEH) is completing the study
- Completion of the study should occur in late 2019/early 2020
- JPA for Signal System at CSAH 5/Nowthen Boulevard and 170th Avenue
- Anoka County submitted a draft JPA for the new signal system
- Ramsey City Attorney reviewed draft JPA
- Anoka-Hennepin Independent School District #11 reviewed draft JPA
- JPA will be presented to City Council for approval in May/June 2019
- Signal system construction scheduled for summer 2019
Timeframe:
Staff estimates 5 minutes will be needed for updates and discussion.
Observations/Alternatives:
NA
Funding Source:
NA
Recommendation:
NA
Action:
No formal action required. For Committee review and discussion purposes only.
Attachments
No file(s) attached.
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Grant Riemer | Grant Riemer | 05/16/2019 09:58 AM |
| Kurt Ulrich | Kurt Ulrich | 05/16/2019 03:27 PM |
- Form Started By:
- Bruce Westby
- Started On:
- 05/16/2019 06:59 AM
- Final Approval Date:
- 05/16/2019