4.5.
CC Regular Session
- Meeting Date:
- 05/28/2019
- Submitted For:
- Bruce Westby
- By:
- Marsha Weidner, Engineering/Public Works
Information
Title
Adopt Resolution #19-108 Authorizing Final Payment to North Valley, Inc. for Improvement Project 18-07, Sunfish Lake Park Parking Lot Improvements.
Purpose/Background:
Resolution and Pay Request Attached
Observations/Alternatives:
Issuing final payment will be contingent on receipt of the following items from North Valley, Inc.:
Following receipt of these items, final payment will be issued.
- IC 134 (Contractor’s Withholding Affidavit showing compliance with the provisions of Minnesota Statute 290.92 requiring withholding state income tax)
- Waiver of Mechanic’s Lien Rights (Affidavits that all claims against North Valley, Inc. by reasons of the contract have been fully paid or satisfactorily secured)
- Consent of Surety to Final Payment (Certification from the contractor’s surety)
Following receipt of these items, final payment will be issued.
Recommendation:
The Senior Engineering Technician has inspected the completed work and recommends final payment to North Valley, Inc. for Improvement Project 18-07; Sunfish Lake Park Parking Lot Improvements in the amount of $23,424.07.
Action:
Motion to adopt Resolution #19-108, Authorizing Final Payment to North Valley, Inc. for Improvement Project 18-07, Sunfish Lake Park Parking Lot Improvements.
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Bruce Westby | Bruce Westby | 05/23/2019 03:44 PM |
| Kurt Ulrich | Kurt Ulrich | 05/23/2019 03:54 PM |
- Form Started By:
- Marsha Weidner
- Started On:
- 05/20/2019 10:58 AM
- Final Approval Date:
- 05/23/2019