Skip to main content

AgendaQuick™

View Agenda Item

4.12.
CC Regular Session
Meeting Date:
06/14/2016
Submitted For:
Grant Riemer
By:
MaryJo Warner, Engineering/Public Works

Information

Title

Report from Public Works Committee dated May 17, 2016
1.  Provide City Council Recommendations for Gibbon Street and 173rd Avenue Drainage Improvements Feasibility Report: No action taken, the discussion was postponed in order to include the residents at a future meeting.
2. Review Updated Estimated Costs for Sunfish Lake Sedimentation Basin Improvements: No action taken, the discussion was postponed in order to include the resident at a future meeting.
3: Provide City Council Recommendation for 2016 Crackseal and Sealcoat Improvements, Improvement Project #16-00 Division A: Ratify the recommendation of the Public Works Committee to recommend that the City Council approve plans as prepared by staff for Improvement Project #16-00, Division A.

 

Purpose/Background:

The Public Works Committee held its regular meeting on May 17, 2016 and discussed the following cases:
1.  Provide City Council Recommendations for Gibbon Street and 173rd Avenue Drainage Improvements Feasibility Report:    Staff reviewed that the feasibility study was conducted in-house and noted this is a feasible project.  The project would include a 3,000 foot storm sewer system with aprons on either end.  The cost is estimated to be about $325,000.  The number of benefiting properties is fairly small.  There have been four property owners that have come forward with wet basements.  The staff recommendation is to consider whether special assessments can pay for most of it, or determine whether funds can be purchased.  Staff has looked online for grants or anything similar that would apply.  While something may become available in the future, there is nothing that would fit the situation.  Currently, it is under consideration to assess the cost to the property owners.  The City will receive little benefit for completing this project and it would not make sense for the City to absorb the cost. Staff did discuss this case with the City Attorney, and learned that the City is under no obligations that it is aware of, to fix this issue.  This home was built before the City was incorporated, which tends to be the case with many of these situations. No action taken due to the homeowners that initially brought this item to the City were not able to attend the meeting and this was for discussion purpose only.
2. Review Updated Estimated Costs for Sunfish Lake Sedimentation Basin Improvements: City Engineer Westby reviewed the staff report.  Staff was directed to develop a cost estimate for the requested improvements.  The cost estimate totals $46,782.75 to construct the settling basin, modify the storm sewer and fill in the drainage swale.  He noted this is in the DNR wetland and when that is impacted, the City must buy double the amount spent in wetland credits. No action taken, the discussion was postponed in order to include the resident at a future meeting.
3. Provide City Council Recommendation for 2016 Crackseal and Sealcoat Improvements, Improvement Project #16-00 Division A:  City Engineer Westby reviewed the staff report, noting the costs listed in the packet are very accurate.  Staff is asking for recommendation to the Council based on these costs.  Motion to ratify the recommendation of the Public Works Committee to recommend that the City Council approve plans as prepared by staff for Improvement Project #16-00, Division A.

 
 

Action:

Motion to ratify the recommendation of the Public Works Committee. 

Attachments

Form Review

Inbox Reviewed By Date
Grant Riemer Grant Riemer 06/10/2016 09:21 AM
Bruce Westby Jo Thieling 06/10/2016 09:54 AM
Kurt Ulrich Jo Thieling 06/10/2016 09:54 AM
Form Started By:
MaryJo Warner
Started On:
06/06/2016 03:47 PM
Final Approval Date:
06/10/2016