VICTOR VALLEY WASTEWATER RECLAMATION AUTHORITY Board Of Commissioners Staff Report |
| TO: | VVWRA Board of Commissioners |
| FROM: | Darron Poulsen, General Manager |
| SUBMITTED BY: | Latif Laari, Director of Engineering & Environmental Compliance |
| DATE: | 05/28/2026 |
| SUBJECT: | Recommendation to adopt Resolution 2026-09 approving the Victor Valley Wastewater Reclamation Authority 2026 Local Hazard Mitigation Plan (LHMP).
|
| Fiscal Impact | N/A |
| Account Code: | |
| Funds Budgeted/ Approved: | No |
STAFF RECOMMENDATION
It is recommended that the Board of Commissioners adopt Resolution 2026-09 approving the Victor Valley Wastewater Reclamation Authority 2026 Local Hazard Mitigation Plan (LHMP) (Exhibit 1)
PREVIOUS ACTION(S)
None
BACKGROUND INFORMATION
The Disaster Mitigation Act of 2000 requires local agencies to prepare and adopt a Local Hazard Mitigation Plan as a prerequisite for eligibility for certain federal disaster assistance and hazard mitigation funding. In October 2025, VVWRA retained Sturdivan Emergency Management Consulting, LLC to assist in the preparation of the Authority’s first Local Hazard Mitigation Plan.
Key components of the Plan include:
- Risk Assessment: Identification and evaluation of major hazards affecting VVWRA, including flooding, drought, wildfire, earthquake, and windstorm events.
- Vulnerability Analysis: Evaluation of critical infrastructure, including treatment plants, lift stations, and interceptor pipelines that serve the High Desert communities.
- Mitigation Strategies: Development of prioritized actions to reduce risk, strengthen system resilience, and protect public health and the environment.
- Climate Resilience: Inclusion of updated data and analysis related to climate change impacts, including increased flood intensity and prolonged drought conditions.
- Plan Maintenance: Procedures for monitoring, evaluating, and updating the Plan to maintain its effectiveness over time.
The LHMP emphasizes proactive planning to reduce long-term risk and strengthen VVWRA’s ability to maintain reliable wastewater treatment services before, during, and after emergency events.
Adoption of the LHMP also reflects the Authority’s commitment to protecting critical infrastructure, maintaining continuity of essential services, and advancing VVWRA’s mission to protect public health and the environment, while supporting strategic objectives related to infrastructure resilience, emergency preparedness, and regulatory compliance.
Adoption of the LHMP also reflects the Authority’s commitment to protecting critical infrastructure, maintaining continuity of essential services, and advancing VVWRA’s mission to protect public health and the environment, while supporting strategic objectives related to infrastructure resilience, emergency preparedness, and regulatory compliance.
FISCAL IMPACT
There is no direct fiscal impact associated with adoption of the LHMP. However, adoption is necessary to maintain eligibility for federal and state hazard mitigation funding, which may help support future capital improvements and emergency response efforts.
There is no direct fiscal impact associated with adoption of the LHMP. However, adoption is necessary to maintain eligibility for federal and state hazard mitigation funding, which may help support future capital improvements and emergency response efforts.