Discussion and possible action to approve and authorize Summit Building & Design the use of Contingency Allowance Expenditure Funds in the amount of $122,966.84 for the Webb County Sheriff Office Renovation Project; and authorize the County Judge sign any relevant documents and any other matters incident thereto. [Account #3867-7230-001-474501 (Construction in Progress) and #3905-7230-001-474501-002 (Finish Out Remodeling)
Issue: This is not a change order and does not increase or decrease the contract amount or the contract's scheduled date of completion.(Please see attached Contingency Allowance Expenditure Authorization No. 2 for additional information).
Solution: Approval to use Contingency funds as follows:
Result: If approved, the Contractor will be authorized to use the owner's contingency amount as approved by Commissioners Court and there will be no increase or decrease to the original contract sum.
Issue: This is not a change order and does not increase or decrease the contract amount or the contract's scheduled date of completion.(Please see attached Contingency Allowance Expenditure Authorization No. 2 for additional information).
Solution: Approval to use Contingency funds as follows:
| Original Contingency Allowance Sum | $375,000.00 |
| Allowance Balance Prior to this authorization | $132,061.00 |
| Allowance sum to be changed by this authorization | $122,966.84 |
| New Allowance balance | $8,946.32 |
Result: If approved, the Contractor will be authorized to use the owner's contingency amount as approved by Commissioners Court and there will be no increase or decrease to the original contract sum.
Background:
N/A
Previous Court Action:
October 10, 2023 - Agenda Item to use Contingency funds in the amount of $242,939.00
Fiscal Impact
- Budget Account Number:
- 0
- Funding Source:
- 0
- Balance:
- 0
Financial Impact:
Account #3867-7230-001-474501 (Construction in Progress) and #3905-7230-001-474501-002 (Finish Out Remodeling)