APPROVAL OF CHANGE ORDER NO.3 FOR ADDITIONAL DAYS FOR ARPA PROJECT NO. 2-SOUTHERN FIRE STATION
Submitted for:
Martha Palacios
Submitted By:
Martha Palacios
Department:
Engineering

Subject:

Discussion and possible action to approve Change Order No. 3, Additional days for Quantcorp Construction LLC., for ARPA Project No. 2 - Webb County Southern Fire Station. The Contract Sum will not be increased by this Change Order; and authorize the Webb County Judge sign any relevant documents, and any other matters incident thereto. [No impact to the account]

Issue: There are items that have impacted the progress of the project, such as the delayed order for a custom-built water pump, the approval of changes for the fence to the septic tank, the air compressor's relocation and furnishing of equipment, and the installation of a water filtration system, the General Contractor requests that the current substantial completion date be extended Thirty (30) calendar days.

Solution: Approval of Change Order which will increase the contract time by thirty (30) days.

Result: Substantial completion date will be from June 9, 2025, to July 9, 2025.

Background:

N/A

Previous Court Action:

N/A

Fiscal Impact

Budget Account Number:
0
Funding Source:
0
Balance:
0

Financial Impact:

NO IMPACT TO THE ACCOUNT

Attachments