30.
Commissioners Court Meeting
- Meeting Date:
- 05/26/2026
- Title:
- APPROVAL FOR A CHANGE ORDER FOR THE ZARAGOZA PARKING LOT
- Submitted for:
- Martha Palacios
- Submitted By:
- Martha Palacios
- Department:
- Engineering
Subject:
Discussion and possible action to approve Change Order No. 1 in the amount of $12,520.00 to CID Group, Inc., for the Zaragoza Street Parking Lot Project. With further action to add 150 calendar days to the project; and have the County Judge sign any relevant documents and any other matters incident thereto. [Account #1001-1130-001-431007-010 (Operational Reserve)]
Issue: Webb County is requesting a security fence at this project. In addition, some concrete pavement will have to be reconstructed along the proposed fence line. Concrete testing and cable re-routing will also be done. The contractor is requesting an additional 150 calendar days.
Solution: Approve Change Order No. 1 and additional days as requested.
Result: Continuation of project. The new substantial completion date will be June 13, 2026.
Issue: Webb County is requesting a security fence at this project. In addition, some concrete pavement will have to be reconstructed along the proposed fence line. Concrete testing and cable re-routing will also be done. The contractor is requesting an additional 150 calendar days.
Solution: Approve Change Order No. 1 and additional days as requested.
Result: Continuation of project. The new substantial completion date will be June 13, 2026.
Background:
N/A
Previous Court Action:
N/A
Fiscal Impact
- Budget Account Number:
- 0
- Funding Source:
- 0
- Balance:
- 0
Financial Impact:
Account #1001-1130-001-431007-010 (Operational Reserve)