9.g.
Commissioners Court Meeting
Meeting Date:
07/13/2026
Title:
Southern Health Facility, Summit Building & Design, Change Order #10
Submitted for:
Guadalupe Ramos
Submitted By:
Guadalupe Ramos
Department:
Economic Development

Subject:

Discussion and possible action to approve Change Order #10 for a decrease to the contract amount with AOC Calton, Ltd. dba Summit Building & Design to reflect final project balance for the Southern Health Facility Project in the amount of FIFTY-FOUR THOUSAND ONE HUNDRED TWENTY-TWO DOLLARS AND EIGHT CENTS ($54,122.08) and further authorizing the Webb County Judge to execute all relevant documents and any other matters incident thereto.

Issue: Several line items within the construction contract, including the Testing Allowance, Owner’s Contingency, and Alternate #2, were not expended fully and funds need to be returned to the Owner.

Solution: Consideration to approve proposed Change Order #10 in order to deduct the unexpended balance from the construction contract with AOC Calton, Ltd, dba Summit Building & Design.
 
Result: If approved, the Economic Development Department will process and submit the change order form.

Background:

n/a

Previous Court Action:

n/a

Fiscal Impact

Budget Account Number:
n/a
Funding Source:
n/a
Balance:
n/a

Financial Impact:

n/a