23.
Commissioners Court Meeting
- Meeting Date:
- 07/27/2026
- Title:
- APPROVE CHANGE ORDER NO. 003
- Submitted for:
- Martha Palacios
- Submitted By:
- Martha Palacios
- Department:
- Engineering
Subject:
Discussion and possible action to authorize Change Order No. 003 for additional days to Stoddard Enterprise LLC., for the Webb County Dean Senator Judith Zaffirini Justice Center Building Envelope Roof Project; and to further authorize the Webb County Judge to sign any relevant documents; and any other matters incident thereto. [No Impact to the Account]
Issue: This change order increases the contract time as per previously approved contingency allowance approvals.
Solution: Approval of change order will increase the contract time by one hundred seventeen (117) days.
Result: Substantial completion date will be moved from July 30, 2026 to November 24, 2026.
Issue: This change order increases the contract time as per previously approved contingency allowance approvals.
- Manufacture delays
- Delays due to court proceedings
- High wind days
- Rain days
Solution: Approval of change order will increase the contract time by one hundred seventeen (117) days.
Result: Substantial completion date will be moved from July 30, 2026 to November 24, 2026.
Background:
N/A
Previous Court Action:
N/A
Fiscal Impact
- Budget Account Number:
- 0
- Funding Source:
- 0
- Balance:
- 0
Financial Impact:
No Impact.