24.
Commissioners Court Meeting
- Meeting Date:
- 07/27/2026
- Title:
- APPROVAL OF CHANGE ORDER NO. 004 FO THE WEBB COUNTY WASTEWATER TREATMENT PLANT
- Submitted for:
- Martha Palacios
- Submitted By:
- Martha Palacios
- Department:
- Engineering
Subject:
Discussion and possible action to authorize Change Order No. 004 for additional days to JMJ Constructors, for the Webb County Wastewater Treatment Plant Project; and to further authorize the Webb County Judge to sign any relevant documents; and any other matters incident thereto. [No Impact to the Account]
Issue: This change order increases the contract time as per previously approved contingency allowance approvals.
Solution: Approval of change order will increase the contract time by ninety-five (95) days.
Result: Substantial completion date will be moved from September 12, 2026, to December 16, 2026.
Issue: This change order increases the contract time as per previously approved contingency allowance approvals.
- Was Piping Replacement & Valve Installation
- Chlorinators & Chlorination Solenoid SCADA Integration
- Post Aeration Blower Addition
- Replacement of existing air control valve
- RAS piping restoration
Solution: Approval of change order will increase the contract time by ninety-five (95) days.
Result: Substantial completion date will be moved from September 12, 2026, to December 16, 2026.
Background:
N/A
Previous Court Action:
N/A
Fiscal Impact
- Budget Account Number:
- 0
- Funding Source:
- 0
- Balance:
- 0
Financial Impact:
No Impact