24.
Commissioners Court Meeting
Meeting Date:
07/27/2026
Title:
APPROVAL OF CHANGE ORDER NO. 004 FO THE WEBB COUNTY WASTEWATER TREATMENT PLANT
Submitted for:
Martha Palacios
Submitted By:
Martha Palacios
Department:
Engineering

Subject:

Discussion and possible action to authorize Change Order No. 004 for additional days to JMJ Constructors, for the Webb County Wastewater Treatment Plant Project; and to further authorize the Webb County Judge to sign any relevant documents; and any other matters incident thereto. [No Impact to the Account]

Issue: This change order increases the contract time as per previously approved contingency allowance approvals.
  • Was Piping Replacement & Valve Installation
  • Chlorinators & Chlorination Solenoid SCADA Integration
  • Post Aeration Blower Addition
  • Replacement of existing air control valve
  • RAS piping restoration

Solution: Approval of change order will increase the contract time by ninety-five (95) days.
 
Result: Substantial completion date will be moved from September 12, 2026, to December 16, 2026.

Background:

N/A

Previous Court Action:

N/A

Fiscal Impact

Budget Account Number:
0
Funding Source:
0
Balance:
0

Financial Impact:

No Impact

Attachments