31.
Commissioners Court Meeting
- Meeting Date:
- 08/10/2026
- Title:
- APPROVAL FOR MATERIAL TESTING FOR THE ACCELERATION AND DECELERATION LANE PROJECT
- Submitted for:
- Martha Palacios
- Submitted By:
- Martha Palacios
- Department:
- Engineering
Subject:
Discussion and possible action to approve Work Authorization No. 2 to Terracon Consultants, Inc., for Material Testing & Observation Services in the amount of $15,173.00 for the Paseo de Los Santos Acceleration and Deceleration Lanes Project; and have the County Judge sign any relevant documents and any other matters incident thereto. [Account #1001-1130-001-432001 (Professional Services)]
Issue: Construction is underway for the Paseo de Los Santos Acceleration and Deceleration Lanes Project and Material Testing services are needed.
Solution: Hiring of Terracon Consultants, Inc., who are part of RFQ 2025-014 for Material Testing, will help proceed with the improvements and repairs for this project. Services will include earthwork / soils testing, Asphaltic concrete testing.
Result: Approval of Contract for Material Testing.
Issue: Construction is underway for the Paseo de Los Santos Acceleration and Deceleration Lanes Project and Material Testing services are needed.
Solution: Hiring of Terracon Consultants, Inc., who are part of RFQ 2025-014 for Material Testing, will help proceed with the improvements and repairs for this project. Services will include earthwork / soils testing, Asphaltic concrete testing.
Result: Approval of Contract for Material Testing.
Background:
N/A
Previous Court Action:
N/A
Fiscal Impact
- Budget Account Number:
- 0
- Funding Source:
- 0
- Balance:
- 0
Financial Impact:
[Account #1001-1130-001-432001 (Professional Services)]